Energy Projects Near You

Kilrubie Wind Farm (21 MW)

Kilrubie Wind Farm is a 21 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 30 November 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
appeal withdrawnstatus in REPD
30 November 2016record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
14 July 2015Application submitted
15 January 2016Appeal lodged
1 November 2016Appeal withdrawn

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
appeal withdrawn
Record last updated
30 November 2016
Operator or applicant
Kilrubie Wind Farm
Planning authority
Scottish Borders
Planning application reference
15/00818/FUL
Appeal reference
PPA-140-2056
Turbines
7
Turbine height
115 m
Address (REPD)
Land North of Upper Stewarton, Eddleston, Peebles
Council area (by location)
Scottish Borders
REPD reference
4770

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cloich Forest Wind Farmwind farm63application submitted1.4
Hag Lawwind farm20refused on appeal3.1
Spurlens Rig Wind Clusterwind farm12refused6.3
Wind Farm at Leithenwater Wind Energy Hubbattery storage10application submitted8.4
Wind Farm at Leithenwater Wind Energy Hubwind farm85.8application submitted8.4
Auchencorth Mosswind farm45refused8.6
Mount Lothian Wind Farmwind farm20.7refused on appeal9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7214, -3.2417).