Girthgate Wind Farm (81.6 MW)

Girthgate Wind Farm is an 81.6 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 31 July 2015. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

81.6 MWwind farm
appeal withdrawnstatus in REPD
31 July 2015record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
1 June 2013Application submitted
10 November 2014Appeal lodged
14 July 2015Appeal withdrawn

Project details

Technology
wind farm
Capacity
81.6 MW
Status (REPD)
appeal withdrawn
Record last updated
31 July 2015
Operator or applicant
Community Windpower
Planning authority
Scottish Government (S36)
Planning application reference
EC00005270
Appeal reference
WIN-140-2
Turbines
24
Address (REPD)
Approximately 3km to the west of Lauder and 5km east of Stow in Berwickshire, Scottish Borders.
Council area (by location)
Scottish Borders
REPD reference
4582

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Muircleugh Farmwind farm21refused on appeal2.7
Rowantree Wind Farmwind farm69refused3.4
Sell Moor Windfarmwind farm47.5refused3.5
Shaw Park Wind Farmwind farm20.7refused on appeal3.6
Longpark Wind Farm Extensionwind farm14application withdrawn5.7
Longparkwind farm38operational5.8
Toddleburnwind farm27.6operational7.0
Dun Law Extensionwind farm29.8operational7.8
Ditcher Law Wind Farmwind farm52.8approved, not built8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7195, -2.8062).