Longpark Wind Farm Extension (14 MW)
Longpark Wind Farm Extension is a 14 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 16 March 2017; the record was last updated on 2 May 2017.
14 MWwind farm
application withdrawnstatus in REPD
2 May 2017record last updated
Scottish Borderscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 8 April 2014 | Application submitted |
| 16 March 2017 | Application withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 14 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 2 May 2017
- Operator or applicant
- Wind Prospect
- Planning authority
- Scottish Borders
- Planning application reference
- 14/00417/S36
- Turbines
- 5
- Turbine height
- 110 m
- Address (REPD)
- Bow Farm Stow Scottish Borders
- Council area (by location)
- Scottish Borders
- REPD reference
- 4576
Who decides
| Applications | Scottish Borders | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 28 (46%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Onshore wind refused | 26 of 43 | 45% |
| Battery storage refused | 2 of 5 | 16% |
| Median time from submission to decision | 51.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 11 / 6 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Longpark | wind farm | 38 | operational | 1.4 |
| Shaw Park Wind Farm | wind farm | 20.7 | refused on appeal | 2.2 |
| Sell Moor Windfarm | wind farm | 47.5 | refused | 2.3 |
| Muircleugh Farm | wind farm | 21 | refused on appeal | 4.6 |
| Girthgate Wind Farm | wind farm | 81.6 | appeal withdrawn | 5.7 |
| Rowantree Wind Farm | wind farm | 69 | refused | 7.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6737, -2.8485).