Shaw Park Wind Farm (20.7 MW)

Shaw Park Wind Farm is a 20.7 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 19 June 2014; the record was last updated on 23 June 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.7 MWwind farm
refused on appealstatus in REPD
23 June 2014record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
30 August 2011Application submitted
8 October 2013Refused by the planning authority
19 June 2014Appeal refused

Project details

Technology
wind farm
Capacity
20.7 MW
Status (REPD)
refused on appeal
Record last updated
23 June 2014
Operator or applicant
J G Shanks & Son Ltd
Planning authority
Scottish Borders
Planning application reference
11/01175/FUL
Appeal reference
14/00002/REF
Turbines
9
Address (REPD)
Land North West And West Of Allanshaws Farmhouse, Galashiels, Scottish Borders
Council area (by location)
Scottish Borders
Time to decision
110 weeks
REPD reference
4074

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sell Moor Windfarmwind farm47.5refused0.1
Longpark Wind Farm Extensionwind farm14application withdrawn2.2
Longparkwind farm38operational2.3
Muircleugh Farmwind farm21refused on appeal2.6
Girthgate Wind Farmwind farm81.6appeal withdrawn3.6
Rowantree Wind Farmwind farm69refused5.7
Toddleburnwind farm27.6operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6898, -2.8278).