Corsbie Moor Wind Farm (27 MW)

Corsbie Moor Wind Farm is a 27 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 28 August 2013; the record was last updated on 6 September 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWwind farm
refused on appealstatus in REPD
6 September 2013record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
29 June 2011Application submitted
3 September 2012Refused by the planning authority
28 August 2013Appeal refused

Project details

Technology
wind farm
Capacity
27 MW
Status (REPD)
refused on appeal
Record last updated
6 September 2013
Operator or applicant
E.ON Climate & Renewables
Planning authority
Scottish Borders
Planning application reference
11/00888/FUL
Appeal reference
12/00046/REF
Turbines
9
Address (REPD)
Corsbie Moor Wind Farm
Council area (by location)
Scottish Borders
Time to decision
62 weeks
REPD reference
3811

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brunta Hill Wind Farmwind farm18.4refused on appeal7.6
Muircleugh Farmwind farm21refused on appeal8.2
Girthgate Wind Farmwind farm81.6appeal withdrawn9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6942, -2.657).