Energy Projects Near You

Moneylaws Hill (11.2 MW wind farm)

Moneylaws Hill is an 11.2 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 10 June 2009; the record was last updated on 10 June 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.2 MWwind farm
application withdrawnstatus in REPD
10 June 2009record last updated
Northumberlandcouncil area

Planning timeline

DateStage
10 June 2009Application withdrawn

Project details

Technology
wind farm
Capacity
11.2 MW
Status (REPD)
application withdrawn
Record last updated
10 June 2009
Operator or applicant
ANGOLD ASSOCIATES
Planning authority
Northumberland
Planning application reference
not recorded
Address (REPD)
Nr Coldstream, Northumberland
Council area (by location)
Northumberland
REPD reference
2600

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Eccles Substation, Ecclesbattery storage50under construction9.4
Bishops Dalbattery storage150application submitted9.4
Toft Hill Windfarmwind farm19refused on appeal9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6057, -2.2031).