Energy Projects Near You

Toft Hill Windfarm (19 MW)

Toft Hill Windfarm is a 19 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 19 October 2008; the record was last updated on 6 December 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19 MWwind farm
refused on appealstatus in REPD
6 December 2010record last updated
Northumberlandcouncil area

Planning timeline

DateStage
15 November 2006Application submitted
27 March 2008Refused by the planning authority
19 October 2008Appeal refused

Project details

Technology
wind farm
Capacity
19 MW
Status (REPD)
refused on appeal
Record last updated
6 December 2010
Operator or applicant
Npower Renewables
Planning authority
Northumberland
Planning application reference
06/B/1001
Turbines
7
Address (REPD)
near village of Gindon, approx 10km SW of Berwick upon Tweed
Council area (by location)
Northumberland
Time to decision
71 weeks
REPD reference
2941

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Moorsyde Wind Farmwind farm16.1refused on appeal3.6
Ancroft Northmoor Wind Farmwind farm16application withdrawn7.0
Barmoor South Wind Farmwind farm13.8operational9.6
Moneylaws Hillwind farm11.2application withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6863, -2.1502).