Barmoor South Wind Farm (13.8 MW)
Barmoor South Wind Farm is a 13.8 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 January 2015; the record was last updated on 20 January 2015.
13.8 MWwind farm
operationalstatus in REPD
20 January 2015record last updated
Northumberlandcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 22 November 2007 | Application submitted |
| 17 December 2007 | Refused by the planning authority |
| 21 January 2010 | Planning permission granted |
| 21 January 2010 | Appeal allowed |
| 1 March 2014 | Construction started |
| 19 January 2015 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 13.8 MW
- Status (REPD)
- operational
- Record last updated
- 20 January 2015
- Operator or applicant
- EDF
- Planning authority
- Northumberland
- Planning application reference
- C/07/00180/CPC
- Turbines
- 6
- Address (REPD)
- Between Ford And Lowick Bowsden Berwick-upon-Tweed
- Council area (by location)
- Northumberland
- Time to decision
- 113 weeks
- REPD reference
- 4163
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Barmoor 06/B/0148 | 27 | 2 March 2006 | refused 27 March 2008 |
Who decides
| Applications | Northumberland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 82 | 10,236 |
| Refused | 31 (38%) | 19% |
| Solar refused | 3 of 36 | 12% |
| Onshore wind refused | 25 of 34 | 45% |
| Battery storage refused | 3 of 12 | 16% |
| Median time from submission to decision | 33.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Corshellach Battery Energy Storage | battery storage | 49.9 | approved, not built | 6.7 |
| Ancroft Northmoor Wind Farm | wind farm | 16 | application withdrawn | 7.1 |
| Moorsyde Wind Farm | wind farm | 16.1 | refused on appeal | 8.2 |
| Toft Hill Windfarm | wind farm | 19 | refused on appeal | 9.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6373, -2.0251).