Corshellach Battery Energy Storage (49.9 MW)

Corshellach Battery Energy Storage is a 49.9 MW battery storage project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 December 2024, not yet built; the record was last updated on 13 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
13 January 2025record last updated
Northumberlandcouncil area

Planning timeline

DateStage
10 July 2024Application submitted
19 December 2024Planning permission granted
19 December 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
13 January 2025
Operator or applicant
RES Limited
Planning authority
Northumberland
Planning application reference
24/01073/APP
Address (REPD)
W/O Berryburn Substation, Forres
Council area (by location)
Northumberland
Time to decision
23 weeks
REPD reference
13290

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ancroft Northmoor Wind Farmwind farm16application withdrawn4.1
Barmoor South Wind Farmwind farm13.8operational6.7
Moorsyde Wind Farmwind farm16.1refused on appeal7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6916, -1.9781).