Energy Projects Near You

Solar, wind and battery projects near Berwick-upon-Tweed (TD15)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TD15 (Northumberland): 4 approved but not yet running. The largest live scheme is Corshellach Battery Energy Storage (49.9 MW battery storage, approved on 19 December 2024, not yet built), 6.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
4approved, not running
0operational

Projects within 10 km of TD15

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ancroft Northmoor Wind Farmwind farmwind farm16application withdrawnupdated Apr 2011Nov 2011—Apr 2011Northumberland5.5
Corshellach Battery Energy Storagebattery storagebattery storage49.9approved, not builtupdated Jan 2025Jul 2024granted Dec 2024Jan 2025Northumberland6.6
Moorsyde Wind Farmwind farmwind farm16.1refused on appealupdated Dec 2010Jan 2005refused Mar 2008Dec 2010Northumberland7.5
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
East Ord Industrial Estate, Tweedmouthrooftop solarrooftop solar0.5approved, not builtupdated Jun 2026Apr 2026granted Jun 2026Jun 2026Northumberland1.7
Berwick Holiday Centre, Magdalen Fieldsrooftop solarrooftop solar0.4approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Northumberland3.2
Castle Hills Farm, Castle Hillsrooftop solarrooftop solar—approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Northumberland3.3

Distance from the average position of the TD15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar303000.9
Wind farm200010
Battery storage1010049.9

MW in pipeline: pending, approved and under-construction capacity.

How Northumberland decides solar, wind and battery applications

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

All projects in Northumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.