Energy Projects Near You

Solar, wind and battery projects near Wooler (NE71)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE71 (Northumberland): 1 operational. The largest scheme is Barmoor South Wind Farm (13.8 MW wind farm, operational since 19 January 2015), 9.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
0approved, not running
1operational

Projects within 10 km of NE71

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Barmoor South Wind Farmwind farmwind farm13.8operationalupdated Jan 2015Nov 2007granted Jan 2010Jan 2015Northumberland9.2
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wooler Ramsey / CLNR ESS2-1battery storagebattery storage0.1decommissionedupdated Oct 2016——Oct 2016Northumberland1.8
Wooler St. Mary / CLNR ESS2-2battery storagebattery storage0.1decommissionedupdated Oct 2016——Oct 2016Northumberland2.3

Distance from the average position of the NE71 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm100100
Battery storage200000

MW in pipeline: pending, approved and under-construction capacity.

How Northumberland decides solar, wind and battery applications

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

All projects in Northumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.