Energy Projects Near You

Solar, wind and battery projects near Chathill (NE67)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE67 (Northumberland): 1 is waiting for a planning decision, 2 operational. The largest live scheme is Middle Mousen (0.5 MW solar farm, application submitted on 13 September 2022, no decision recorded; REPD status may be out of date), 9.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
1awaiting a decision
0approved, not running
2operational

Projects within 10 km of NE67

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wandylawwind farmwind farm20.5operationalupdated Apr 2015Aug 2006granted Feb 2008Apr 2015Northumberland5.0
Middlemoorwind farmwind farm54operationalupdated Mar 2014Dec 2005granted Aug 2008Mar 2014Northumberland6.5
Charlton Mireswind turbinewind turbine1.5refusedupdated Oct 2015Jun 2014refused Sep 2015Oct 2015Northumberland6.9
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Middle Mousensolar farmsolar farm0.5application submitted may be out of dateupdated Sep 2022Sep 2022—Sep 2022Northumberland9.0

Distance from the average position of the NE67 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm110000.5
Wind farm200200
Wind turbine100010

MW in pipeline: pending, approved and under-construction capacity.

How Northumberland decides solar, wind and battery applications

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

All projects in Northumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE67, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.