Energy Projects Near You

Wandylaw (20.5 MW wind farm)

Wandylaw is a 20.5 MW wind farm project in Northumberland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 July 2013; the record was last updated on 24 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.5 MWwind farm
operationalstatus in REPD
24 April 2015record last updated
Northumberlandcouncil area

Planning timeline

DateStage
1 August 2006Application submitted
24 October 2007Refused by the planning authority
10 February 2008Planning permission granted
10 February 2008Appeal allowed
30 May 2012Construction started
30 July 2013Operational

Project details

Technology
wind farm
Capacity
20.5 MW
Status (REPD)
operational
Record last updated
24 April 2015
Operator or applicant
Blue Energy
Planning authority
Northumberland
Planning application reference
06/B/0765
Turbines
10
Address (REPD)
The Ellingham Estate, 3.5km West of the Village of Ellingham
Council area (by location)
Northumberland
Time to decision
80 weeks
REPD reference
4250

Who decides

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Middlemoorwind farm54operational2.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5196, -1.7642).