Solar, wind and battery projects near Seahouses (NE68)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NE68 (Northumberland): 1 is waiting for a planning decision, 1 approved but not yet running, 1 operational. The largest live scheme is Middle Mousen (0.5 MW solar farm, application submitted on 13 September 2022, no decision recorded; REPD status may be out of date), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
1awaiting a decision
1approved, not running
1operational

Projects within 10 km of NE68

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wandylawwind farmwind farm20.5operationalupdated Apr 2015Aug 2006granted Feb 2008Apr 2015Northumberland9.3
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Middle Mousensolar farmsolar farm0.5application submitted may be out of dateupdated Sep 2022Sep 2022—Sep 2022Northumberland9.5
Coastal Grains, Station Roadsolar farmsolar farm—approved, not builtupdated Jan 2024Sep 2023granted Jan 2024Jan 2024Northumberland9.7

Distance from the average position of the NE68 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm211000.5
Wind farm100100

MW in pipeline: pending, approved and under-construction capacity.

How Northumberland decides solar, wind and battery applications

ApplicationsNorthumberlandUK
Decided applications (solar, wind, battery)8210,236
Refused31 (38%)19%
Solar refused3 of 3612%
Onshore wind refused25 of 3445%
Battery storage refused3 of 1216%
Median time from submission to decision33.3 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

All projects in Northumberland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NE68, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.