Energy Projects Near You

Wind Turbines at Se/O Reston Hill Farmhouse (20 MW)

Wind Turbines at Se/O Reston Hill Farmhouse is a 20 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 29 August 2013; the record was last updated on 30 August 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWwind farm
refused on appealstatus in REPD
30 August 2013record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
30 October 2012Application submitted
29 August 2013Refused by the planning authority
29 August 2013Appeal refused

Project details

Technology
wind farm
Capacity
20 MW
Status (REPD)
refused on appeal
Record last updated
30 August 2013
Operator or applicant
Energiekontor UK
Planning authority
Scottish Borders
Planning application reference
12/01348/FUL
Appeal reference
13/00011/NONDET
Turbines
10
Address (REPD)
Se/O Reston Hill Farmhouse, Horn Burn Wind Farm, Eyemouth, Borders, TD14
Council area (by location)
Scottish Borders
Time to decision
43 weeks
Name in REPD
HORN BURN WIND FARM - WIND TURBINES
REPD reference
3914

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Monashee Farm, Drakemyrewind farm24application submitted9.0
Monashee Wind Farmwind farm24application submitted9.0
Monashee Wind Farmwind farm15application withdrawn9.6
Drone Hillwind farm28.6operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8286, -2.1612).