Wind Turbines at Se/O Reston Hill Farmhouse (20 MW)
Wind Turbines at Se/O Reston Hill Farmhouse is a 20 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 29 August 2013; the record was last updated on 30 August 2013.
20 MWwind farm
refused on appealstatus in REPD
30 August 2013record last updated
Scottish Borderscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 30 October 2012 | Application submitted |
| 29 August 2013 | Refused by the planning authority |
| 29 August 2013 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 20 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 30 August 2013
- Operator or applicant
- Energiekontor UK
- Planning authority
- Scottish Borders
- Planning application reference
- 12/01348/FUL
- Appeal reference
- 13/00011/NONDET
- Turbines
- 10
- Address (REPD)
- Se/O Reston Hill Farmhouse, Horn Burn Wind Farm, Eyemouth, Borders, TD14
- Council area (by location)
- Scottish Borders
- Time to decision
- 43 weeks
- Name in REPD
- HORN BURN WIND FARM - WIND TURBINES
- REPD reference
- 3914
Who decides
| Applications | Scottish Borders | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 28 (46%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Onshore wind refused | 26 of 43 | 45% |
| Battery storage refused | 2 of 5 | 16% |
| Median time from submission to decision | 51.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 11 / 6 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Monashee Farm, Drakemyre | wind farm | 24 | application submitted | 9.0 |
| Monashee Wind Farm | wind farm | 24 | application submitted | 9.0 |
| Monashee Wind Farm | wind farm | 15 | application withdrawn | 9.6 |
| Drone Hill | wind farm | 28.6 | operational | 9.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8286, -2.1612).