Monashee Wind Farm (15 MW)

Monashee Wind Farm is a 15 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 25 June 2013; the record was last updated on 11 July 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
application withdrawnstatus in REPD
11 July 2013record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
6 April 2012Application submitted
25 June 2013Application withdrawn

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
application withdrawn
Record last updated
11 July 2013
Operator or applicant
Element Power
Planning authority
Scottish Borders
Planning application reference
12/00431/FUL
Turbines
6
Council area (by location)
Scottish Borders
REPD reference
3884

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Monashee Farm, Drakemyrewind farm24application submitted2.2
Monashee Wind Farmwind farm24application submitted2.2
Quixwood Moorwind farm29.9operational3.3
Monasheewind farm15application withdrawn3.7
Howpark Solar Farmsolar farm15approved, not built3.9
Penmanshiel Wind Farmwind farm28.7operational5.2
Howpark Wind Farmwind farm16operational5.5
Bowshiel Farm Solar Farmsolar farm165application submitted5.5
Bowshiel Farmbattery storage80application submitted5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.851, -2.3089).