Quixwood Moor (29.9 MW wind farm)

Quixwood Moor is a 29.9 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 9 March 2017; the record was last updated on 4 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWwind farm
operationalstatus in REPD
4 April 2017record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
22 December 2011Application submitted
2 April 2013Planning permission granted
6 January 2016Construction started
9 March 2017Operational

Project details

Technology
wind farm
Capacity
29.9 MW
Status (REPD)
operational
Record last updated
4 April 2017
Operator or applicant
NTR PLC
Planning authority
Scottish Borders
Planning application reference
11/01662/FUL
Turbines
13
Address (REPD)
Scottish Borders
Council area (by location)
Scottish Borders
Time to decision
67 weeks
REPD reference
4179

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bowshiel Farmbattery storage80application submitted2.8
Bowshiel Farm Solar Farmsolar farm165application submitted2.8
Blackburn Mill Farm, Grantshousewind farm16.8approved, not built2.9
Monasheewind farm15application withdrawn3.2
Monashee Wind Farmwind farm15application withdrawn3.3
Blackburn Farmwind farm21refused3.4
Penmanshiel Wind Farmwind farm28.7operational3.8
Monashee Wind Farmwind farm24application submitted4.0
Monashee Farm, Drakemyrewind farm24application submitted4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8674, -2.3527).