Energy Projects Near You

Blackburn Farm (21 MW wind farm)

Blackburn Farm is a 21 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 6 August 2012; the record was last updated on 31 August 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWwind farm
refusedstatus in REPD
31 August 2012record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
1 August 2011Application submitted
6 August 2012Refused by the planning authority

Project details

Technology
wind farm
Capacity
21 MW
Status (REPD)
refused
Record last updated
31 August 2012
Operator or applicant
Volkswind UK Ltd
Planning authority
Scottish Borders
Planning application reference
11/01077/FUL
Turbines
6
Address (REPD)
Grantshouse Duns Scottish Borders TD11 3LF
Council area (by location)
Scottish Borders
Time to decision
53 weeks
REPD reference
3411

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blackburn Mill Farm, Grantshousewind farm16.8approved, not built0.5
Bowshiel Farm Solar Farmsolar farm165application submitted0.8
Bowshiel Farmbattery storage80application submitted0.8
Penmanshiel Wind Farmwind farm28.7operational1.9
Monasheewind farm15application withdrawn3.0
Quixwood Moorwind farm29.9operational3.4
Hoprigshiels Community Wind Farmwind farm6.9operational3.5
Howpark Solar Farmsolar farm15approved, not built4.0
Kinegar Quarrywind farm5operational4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8976, -2.3521).