Penmanshiel Wind Farm (28.7 MW)

Penmanshiel Wind Farm is a 28.7 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 July 2016; the record was last updated on 31 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28.7 MWwind farm
operationalstatus in REPD
31 May 2016record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
27 October 2011Application submitted
15 September 2012Refused by the planning authority
16 October 2013Planning permission granted
16 October 2013Appeal allowed
6 May 2015Construction started
1 July 2016Operational

Project details

Technology
wind farm
Capacity
28.7 MW
Status (REPD)
operational
Record last updated
31 May 2016
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Scottish Borders
Planning application reference
11/01464/FUL
Appeal reference
12/00043/NONDET
Turbines
14
Address (REPD)
Land East Of Penmanshiel Farmhouse Grantshouse Scottish Borders
Council area (by location)
Scottish Borders
Time to decision
103 weeks
REPD reference
4600

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Monasheewind farm15application withdrawn1.5
Blackburn Farmwind farm21refused1.9
Blackburn Mill Farm, Grantshousewind farm16.8approved, not built2.2
Howpark Solar Farmsolar farm15approved, not built2.2
Bowshiel Farm Solar Farmsolar farm165application submitted2.4
Bowshiel Farmbattery storage80application submitted2.4
Howpark Wind Farmwind farm16operational2.5
Drone Hillwind farm28.6operational3.7
Quixwood Moorwind farm29.9operational3.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8969, -2.3213).