Howpark Wind Farm (16 MW)

Howpark Wind Farm is a 16 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2024; the record was last updated on 14 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWwind farm
operationalstatus in REPD
14 May 2026record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
23 August 2016Application submitted
24 April 2017Refused by the planning authority
19 July 2017Appeal lodged
24 April 2018Planning permission granted
24 April 2018Appeal allowed
28 March 2021Construction started
1 January 2024Operational

Project details

Technology
wind farm
Capacity
16 MW
Status (REPD)
operational
Record last updated
14 May 2026
Operator or applicant
Eurowind (UK) Limited
Planning authority
Scottish Borders
Planning application reference
16/00980/FUL
Appeal reference
PPA-140-2060
Turbines
8
Turbine height
100 m
Address (REPD)
Land North of Howpark Farm, Grantshouse, Duns
Council area (by location)
Scottish Borders
Time to decision
87 weeks
REPD reference
6214

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Drone Hillwind farm28.6operational1.2
Howpark Solar Farmsolar farm15approved, not built1.6
Monasheewind farm15application withdrawn2.4
Penmanshiel Wind Farmwind farm28.7operational2.5
Monashee Wind Farmwind farm24application submitted3.5
Monashee Farm, Drakemyrewind farm24application submitted3.5
Blackburn Farmwind farm21refused4.4
Blackburn Mill Farm, Grantshousewind farm16.8approved, not built4.7
Bowshiel Farm Solar Farmsolar farm165application submitted4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8976, -2.281).