Energy Projects Near You

Monashee Wind Farm (24 MW)

Monashee Wind Farm is a 24 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 17 April 2025, no decision recorded; the record was last updated on 16 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWwind farm
application submittedstatus in REPD
16 May 2025record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
17 April 2025Application submitted

Project details

Technology
wind farm
Capacity
24 MW
Status (REPD)
application submitted
Record last updated
16 May 2025
Operator or applicant
Green Switch Capital Limited
Planning authority
Scottish Borders
Planning application reference
25/00473/FUL
Turbines
4
Turbine height
180 m
Address (REPD)
Monashee Farm, Drakemyre, Grantshouse, Duns
Council area (by location)
Scottish Borders
REPD reference
14154

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Monashee Farm, Drakemyrewind farm24application submitted<0.1
Howpark Solar Farmsolar farm15approved, not built2.1
Monashee Wind Farmwind farm15application withdrawn2.2
Monasheewind farm15application withdrawn2.4
Howpark Wind Farmwind farm16operational3.5
Drone Hillwind farm28.6operational3.8
Penmanshiel Wind Farmwind farm28.7operational4.0
Quixwood Moorwind farm29.9operational4.0
Blackburn Mill Farm, Grantshousewind farm16.8approved, not built5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8666, -2.2879).