Energy Projects Near You

Hoprigshiels Community Wind Farm (6.9 MW)

Hoprigshiels Community Wind Farm is a 6.9 MW wind farm project in Scottish Borders, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 14 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
operationalstatus in REPD
14 July 2017record last updated
Scottish Borderscouncil area

Planning timeline

DateStage
6 June 2011Application submitted
20 November 2014Planning permission granted
11 January 2016Construction started
31 March 2017Operational

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
operational
Record last updated
14 July 2017
Operator or applicant
Private Developer
Planning authority
Scottish Borders
Planning application reference
11/00664/FUL
Turbines
3
Address (REPD)
Land North And South Of 1 Whinhouse, Hoprigshiels, Cockburnspath, Scottish Borders
Council area (by location)
Scottish Borders
Time to decision
180 weeks
REPD reference
4575

Who decides

ApplicationsScottish BordersUK
Decided applications (solar, wind, battery)6110,236
Refused28 (46%)19%
Solar refused0 of 1312%
Onshore wind refused26 of 4345%
Battery storage refused2 of 516%
Median time from submission to decision51.3 weeks17.0 weeks
Appeals lodged / allowed11 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kinegar Quarrywind farm5operational2.3
Ferneylea Farmwind farm18application withdrawn2.7
Blackburn Farmwind farm21refused3.5
Blackburn Mill Farm, Grantshousewind farm16.8approved, not built3.7
Bowshiel Farm Solar Farmsolar farm165application submitted3.8
Bowshiel Farmbattery storage80application submitted3.8
Aikengall IIa Community Wind Farmwind farm81.7operational4.9
Penmanshiel Wind Farmwind farm28.7operational5.1
Braxbess Battery Storagebattery storage650approved, not built5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.9207, -2.3915).