Energy Projects Near You

Dunbar Grid Substation (49.9 MW battery storage)

Dunbar Grid Substation is a 49.9 MW battery storage project in East Lothian, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 October 2024, not yet built; the record was last updated on 22 October 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
22 October 2024record last updated
East Lothiancouncil area

Planning timeline

DateStage
15 January 2024Application submitted
1 October 2024Planning permission granted
1 October 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
22 October 2024
Operator or applicant
FRV TH Powertek Limited
Planning authority
East Lothian
Planning application reference
23/01519/PM
Address (REPD)
The N/O Dunbar Grid Substation, Dunbar
Council area (by location)
East Lothian
Time to decision
37 weeks
Name in REPD
Dunbar Grid Substation - Battery Storage
REPD reference
13864

Who decides

ApplicationsEast LothianUK
Decided applications (solar, wind, battery)1510,236
Refused1 (7%)19%
Solar refused0 of 612%
Onshore wind refused1 of 745%
Battery storage refused0 of 216%
Median time from submission to decision34.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Springfield Solar Farm & Battery Energy Storagesolar farm165application submitted2.0
Crystal Rig Wind Farm Phase IIIwind farm13.8operational6.3
Aikengall, Innerwickbattery storage19.9approved, not built7.4
Crystal Rig Extension IIwind farm20.7operational7.5
Braxbess Battery Storagebattery storage650approved, not built8.1
Aikengall II, Wester Dod Community Wind Farmwind farm60.8operational8.5
Aikengallwind farm48operational8.5
Crystal Rig Wind Farm Phase IVwind farm48under construction8.9
Crystal Rig Wind Farm Phase 2awind farm138operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.979, -2.5714).