Solar, wind and battery projects near Musselburgh (EH21)
18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EH21 (East Lothian): 3 are waiting for a planning decision, 14 approved but not yet running, 1 operational. The largest live scheme is Cockenzie Battery Storage System - Site A (240 MW battery storage, approved on 23 July 2025, not yet built), 6.1 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 24.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of EH21
Projects of 1 MW and more (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Smeaton Battery Energy Storage Systembattery storage | battery storage | 228 | approved, not builtupdated Oct 2024 | Mar 2023 | granted Aug 2024 | Oct 2024 | East Lothian | 2.8 |
| Dolphingstone Farmbattery storage | battery storage | 63 | approved, not builtupdated Oct 2025 | Nov 2023 | granted Jul 2025 | Oct 2025 | East Lothian | 3.5 |
| Salters Battery Energy Storage Systembattery storage | battery storage | 200 | approved, not builtupdated Jul 2025 | Aug 2024 | granted May 2025 | Jul 2025 | Midlothian | 4.8 |
| Cockenzie Battery Storage System - Site Abattery storage | battery storage | 240 | approved, not builtupdated Oct 2025 | Aug 2023 | granted Jul 2025 | Oct 2025 | East Lothian | 6.1 |
| Cockenzie Battery Storage System - Site Bbattery storage | battery storage | 102 | approved, not builtupdated Oct 2025 | Nov 2024 | granted Jul 2025 | Oct 2025 | East Lothian | 6.1 |
| Existing Kaimes Substation, Old Burdiehouse Roadbattery storage | battery storage | 49.9 | application submitted may be out of dateupdated Apr 2024 | Mar 2024 | — | Apr 2024 | City of Edinburgh | 8.7 |
Smaller schemes under 1 MW, mostly rooftop solar (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Old Dalkeith Road, Danderhallrooftop solar | rooftop solar | 0.1 | approved, not built may be out of dateupdated Mar 2022 | Mar 2022 | granted Apr 2022 | Mar 2022 | Midlothian | 4.8 |
| Edinburgh College, Dalhousie Roadrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | Midlothian | 6.5 |
| Meadow Stores, Ormistonsolar farm | solar farm | 0.2 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | East Lothian | 7.1 |
| Royal Commonwealth Pool, Dalkeith Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2026 | Nov 2025 | granted Jan 2026 | Mar 2026 | City of Edinburgh | 7.9 |
| Seton Sands, Holiday Villagerooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jul 2023 | May 2023 | granted Jun 2023 | Jul 2023 | East Lothian | 8.1 |
| Butlerfield Industrial Estaterooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Midlothian | 8.6 |
| City of Edinburgh Council Buildingsrooftop solar | rooftop solar | 0.2 | operationalupdated Nov 2022 | Apr 2020 | granted May 2020 | Nov 2022 | City of Edinburgh | 8.8 |
| George Squarerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | City of Edinburgh | 9.0 |
| Omni Centre, Leith Streetrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Nov 2022 | Sep 2022 | granted Nov 2022 | Nov 2022 | City of Edinburgh | 9.0 |
| Ocean Point 2 - 404 Bed Student Accommodation & 120 Apartmentsrooftop solar | rooftop solar | 0.1 | application submitted may be out of dateupdated Oct 2023 | Sep 2023 | — | Oct 2023 | City of Edinburgh | 9.3 |
| Sainsburys Supermarket, Straiton Mainsrooftop solar | rooftop solar | 0.6 | application submitted may be out of dateupdated Aug 2023 | Aug 2023 | — | Aug 2023 | Midlothian | 9.4 |
| Canaan Lane Primary School, Canaan Lanerooftop solar | rooftop solar | 0.1 | approved, not builtupdated Sep 2025 | Aug 2025 | granted Sep 2025 | Sep 2025 | City of Edinburgh | 9.8 |
Distance from the average position of the EH21 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 1 | 0 | 1 | 0 | 0 | 0.2 |
| Rooftop solar | 11 | 2 | 8 | 1 | 0 | 2.5 |
| Battery storage | 6 | 1 | 5 | 0 | 0 | 883 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Forthwind | 20 | approved, not builtupdated Aug 2023 | 24.3 |
| Levenmouth demonstration turbine (Fife Energy Park) | 7 | operationalupdated Nov 2018 | 25.4 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How East Lothian decides solar, wind and battery applications
| Applications | East Lothian | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 1 (7%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Onshore wind refused | 1 of 7 | 45% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 34.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EH21, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.