Solar, wind and battery projects near Leven (KY8)
22 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KY8 (Fife): 12 approved but not yet running, 5 operational. The largest live scheme is Wemyss Estate - Randolph Solar Farm & Battery Energy Storage (50 MW solar farm, approved on 24 May 2022, not yet built), 7.7 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 4.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of KY8
Projects of 1 MW and more (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Banbeath Industrial Estate Solar Arraysolar farm | solar farm | 4.2 | under constructionupdated Jun 2022 | Aug 2021 | granted Sep 2022 | Jun 2022 | Fife | 0.9 |
| Wester Durie Farmwind turbine | wind turbine | 2.3 | refusedupdated Nov 2014 | Dec 2013 | refused Aug 2014 | Nov 2014 | Fife | 1.4 |
| Duniface Gas Peaking Plantbattery storage | battery storage | 49.9 | approved, not builtupdated Oct 2024 | May 2024 | granted Sep 2024 | Oct 2024 | Fife | 2.0 |
| Clattowind farm | wind farm | 30 | refusedupdated Nov 2015 | Sep 2003 | refused Nov 2004 | Nov 2015 | Fife | 4.6 |
| Earlseatwind farm | wind farm | 18.4 | operationalupdated Aug 2014 | Sep 2010 | granted Mar 2012 | Aug 2014 | Fife | 5.0 |
| Devon Woodwind farm | wind farm | 12.5 | refused on appealupdated Dec 2012 | Jun 2010 | refused Apr 2012 | Dec 2012 | Fife | 5.1 |
| Clatto Farm Turbineswind farm | wind farm | 6 | refused on appealupdated Dec 2012 | May 2010 | refused Apr 2012 | Dec 2012 | Fife | 6.0 |
| Wemyss Estate - Randolph Solar Farm & Battery Energy Storagesolar farm | solar farm | 50 | approved, not builtupdated Jun 2022 | Mar 2021 | granted May 2022 | Jun 2022 | Fife | 7.7 |
| Wemyss Estate - Randolph Solar Farm & Battery Energy Storagebattery storage | battery storage | 25 | approved, not builtupdated Jun 2022 | Mar 2021 | granted May 2022 | Jun 2022 | Fife | 9.2 |
| West Strathore Solar Limitedsolar farm | solar farm | 5 | operationalupdated Jul 2017 | Jul 2015 | granted Nov 2015 | Jul 2017 | Fife | 9.3 |
| Skeddoway Farm Wind Turbinewind turbine | wind turbine | 1.5 | operationalupdated Jul 2015 | Feb 2013 | granted Jan 2014 | Jul 2015 | Fife | 9.7 |
| Land North of Balbeggie Avenuesolar farm | solar farm | 12 | approved, not built may be out of dateupdated Sep 2020 | Oct 2015 | granted Mar 2016 | Sep 2020 | Fife | 9.7 |
| Noble Foodswind turbine | wind turbine | 1.5 | operationalupdated Oct 2016 | May 2011 | granted Nov 2011 | Oct 2016 | Fife | 9.8 |
| Land North of Thornton Roadbattery storage | battery storage | 19.9 | approved, not built may be out of dateupdated Apr 2020 | Nov 2015 | granted Feb 2016 | Apr 2020 | Fife | 9.9 |
| Middle Balbeggiesolar farm | solar farm | 5 | operationalupdated Apr 2018 | Sep 2015 | granted Dec 2015 | Apr 2018 | Fife | 10.0 |
| Gathercauldwind farm | wind farm | 15.6 | refusedupdated Dec 2009 | Jun 2007 | refused Jun 2009 | Dec 2009 | Fife | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Elmpark Sawmill, Leven Millsrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Fife | 0.4 |
| Banbeath Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2020 | Jan 2020 | granted Apr 2020 | Jun 2020 | Fife | 0.5 |
| Energy Storage Batterybattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2025 | May 2025 | granted May 2025 | Jul 2025 | Fife | 0.6 |
| Donaldson Timber Engineering, Muiredge Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | Fife | 3.2 |
| Flexel International, Telford Roadsolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Fife | 8.2 |
| Westwood One, James Watt Avenuesolar farm | solar farm | 0.5 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | Fife | 8.8 |
Distance from the average position of the KY8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 5 | 2 | 0 | 66.9 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 1.3 |
| Wind farm | 5 | 0 | 0 | 1 | 4 | 0 |
| Wind turbine | 3 | 0 | 0 | 2 | 1 | 0 |
| Battery storage | 4 | 0 | 4 | 0 | 0 | 95 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Forthwind | 20 | approved, not builtupdated Aug 2023 | 4.8 |
| Levenmouth demonstration turbine (Fife Energy Park) | 7 | operationalupdated Nov 2018 | 5.3 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Fife decides solar, wind and battery applications
| Applications | Fife | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 17 (19%) | 19% |
| Solar refused | 0 of 36 | 12% |
| Onshore wind refused | 16 of 30 | 45% |
| Battery storage refused | 1 of 25 | 16% |
| Median time from submission to decision | 24.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KY8, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.