Energy Projects Near You

Clatto (30 MW wind farm)

Clatto is a 30 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 1 November 2004; the record was last updated on 24 November 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWwind farm
refusedstatus in REPD
24 November 2015record last updated
Fifecouncil area

Planning timeline

DateStage
24 September 2003Application submitted
1 November 2004Refused by the planning authority

Project details

Technology
wind farm
Capacity
30 MW
Status (REPD)
refused
Record last updated
24 November 2015
Operator or applicant
Scottish Power Renewables
Planning authority
Fife
Planning application reference
03/03397/EEIA
Appeal reference
P/PPA/250/507
Address (REPD)
Kennoway Fife
Council area (by location)
Fife
Time to decision
58 weeks
REPD reference
3180

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Devon Woodwind farm12.5refused on appeal0.8
Clatto Farm Turbineswind farm6refused on appeal1.5
Duniface Gas Peaking Plantbattery storage49.9approved, not built3.9
Earlseatwind farm18.4operational6.9
Solar Panels & BESSsolar farm49.9application submitted7.3
Gathercauldwind farm15.6refused8.7
Ferrymuirbattery storage49.9under construction8.8
Wemyss Estate - Randolph Solar Farm & Battery Energy Storagesolar farm50approved, not built8.9
Fife Tractors, Drum Roadbattery storage12.5refused9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2331, -3.0501).