Clatto (30 MW wind farm)
Clatto is a 30 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 1 November 2004; the record was last updated on 24 November 2015.
30 MWwind farm
refusedstatus in REPD
24 November 2015record last updated
Fifecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 24 September 2003 | Application submitted |
| 1 November 2004 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 30 MW
- Status (REPD)
- refused
- Record last updated
- 24 November 2015
- Operator or applicant
- Scottish Power Renewables
- Planning authority
- Fife
- Planning application reference
- 03/03397/EEIA
- Appeal reference
- P/PPA/250/507
- Address (REPD)
- Kennoway Fife
- Council area (by location)
- Fife
- Time to decision
- 58 weeks
- REPD reference
- 3180
Who decides
| Applications | Fife | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 17 (19%) | 19% |
| Solar refused | 0 of 36 | 12% |
| Onshore wind refused | 16 of 30 | 45% |
| Battery storage refused | 1 of 25 | 16% |
| Median time from submission to decision | 24.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Devon Wood | wind farm | 12.5 | refused on appeal | 0.8 |
| Clatto Farm Turbines | wind farm | 6 | refused on appeal | 1.5 |
| Duniface Gas Peaking Plant | battery storage | 49.9 | approved, not built | 3.9 |
| Earlseat | wind farm | 18.4 | operational | 6.9 |
| Solar Panels & BESS | solar farm | 49.9 | application submitted | 7.3 |
| Gathercauld | wind farm | 15.6 | refused | 8.7 |
| Ferrymuir | battery storage | 49.9 | under construction | 8.8 |
| Wemyss Estate - Randolph Solar Farm & Battery Energy Storage | solar farm | 50 | approved, not built | 8.9 |
| Fife Tractors, Drum Road | battery storage | 12.5 | refused | 9.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2331, -3.0501).