Devon Wood (12.5 MW wind farm)
Devon Wood is a 12.5 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 22 November 2012; the record was last updated on 7 December 2012.
12.5 MWwind farm
refused on appealstatus in REPD
7 December 2012record last updated
Fifecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 29 June 2010 | Application submitted |
| 18 April 2012 | Refused by the planning authority |
| 22 November 2012 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 12.5 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 7 December 2012
- Operator or applicant
- East Fife Wind Energy
- Planning authority
- Fife
- Planning application reference
- 10/02183/EIA
- Appeal reference
- 12/00056/REF
- Turbines
- 5
- Address (REPD)
- between Kennoway and Kingskettle, Fife
- Council area (by location)
- Fife
- Time to decision
- 94 weeks
- REPD reference
- 2760
Who decides
| Applications | Fife | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 17 (19%) | 19% |
| Solar refused | 0 of 36 | 12% |
| Onshore wind refused | 16 of 30 | 45% |
| Battery storage refused | 1 of 25 | 16% |
| Median time from submission to decision | 24.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Clatto | wind farm | 30 | refused | 0.8 |
| Clatto Farm Turbines | wind farm | 6 | refused on appeal | 0.9 |
| Duniface Gas Peaking Plant | battery storage | 49.9 | approved, not built | 4.6 |
| Solar Panels & BESS | solar farm | 49.9 | application submitted | 6.8 |
| Earlseat | wind farm | 18.4 | operational | 7.7 |
| Ferrymuir | battery storage | 49.9 | under construction | 8.0 |
| Gathercauld | wind farm | 15.6 | refused | 8.0 |
| Fife Tractors, Drum Road | battery storage | 12.5 | refused | 8.3 |
| Over Rankeilour Farm Solar Farm | solar farm | 29.9 | application submitted | 9.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2397, -3.0441).