Energy Projects Near You

Ferrymuir (49.9 MW battery storage)

Ferrymuir is a 49.9 MW battery storage project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 29 July 2022; the record was last updated on 29 July 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
under constructionstatus in REPD
29 July 2022record last updated
Fifecouncil area

Planning timeline

DateStage
23 September 2019Application submitted
10 January 2020Planning permission granted
29 July 2022Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
29 July 2022
Operator or applicant
Gore Street Energy Storage Fund
Planning authority
Fife
Planning application reference
19/02750/FULL
Address (REPD)
Land west of Ferrymuir, South of Westfield Road, Cupar,
Council area (by location)
Fife
Time to decision
16 weeks
REPD reference
7371

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fife Tractors, Drum Roadbattery storage12.5refused0.8
Over Rankeilour Farm Solar Farmsolar farm29.9application submitted2.4
Solar Panels & BESSsolar farm49.9application submitted4.1
Gathercauldwind farm15.6refused7.2
Clatto Farm Turbineswind farm6refused on appeal7.4
Devon Woodwind farm12.5refused on appeal8.0
Clattowind farm30refused8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3111, -3.0256).