Energy Projects Near You

Gathercauld (15.6 MW wind farm)

Gathercauld is a 15.6 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 17 June 2009; the record was last updated on 2 December 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15.6 MWwind farm
refusedstatus in REPD
2 December 2009record last updated
Fifecouncil area

Planning timeline

DateStage
1 June 2007Application submitted
17 June 2009Refused by the planning authority

Project details

Technology
wind farm
Capacity
15.6 MW
Status (REPD)
refused
Record last updated
2 December 2009
Operator or applicant
Energiekontor UK
Planning authority
Fife
Planning application reference
07/01813/EEIA
Turbines
13
Address (REPD)
Gathercauld, Ceres, Fife
Council area (by location)
Fife
Time to decision
107 weeks
REPD reference
3513

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cameron Reservoirsolar farm5abandoned5.2
Ferrymuirbattery storage49.9under construction7.2
Fife Tractors, Drum Roadbattery storage12.5refused8.0
Devon Woodwind farm12.5refused on appeal8.0
Clatto Farm Turbineswind farm6refused on appeal8.2
Lingo Wind Farmwind farm12.5refused on appeal8.7
Clattowind farm30refused8.7
Over Rankeilour Farm Solar Farmsolar farm29.9application submitted9.6
Solar Panels & BESSsolar farm49.9application submitted9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2745, -2.9301).