Energy Projects Near You

Lingo Wind Farm (12.5 MW)

Lingo Wind Farm is a 12.5 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 4 October 2013; the record was last updated on 8 October 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.5 MWwind farm
refused on appealstatus in REPD
8 October 2013record last updated
Fifecouncil area

Planning timeline

DateStage
23 January 2012Application submitted
31 January 2013Refused by the planning authority
4 October 2013Appeal refused

Project details

Technology
wind farm
Capacity
12.5 MW
Status (REPD)
refused on appeal
Record last updated
8 October 2013
Operator or applicant
Lingo Wind Energy Ltd
Planning authority
Fife
Planning application reference
12/00129/EIA
Appeal reference
PPA-250-2153
Turbines
5
Address (REPD)
Lingo Farm, Lingo, Fife
Council area (by location)
Fife
Time to decision
53 weeks
REPD reference
3844

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cameron Reservoirsolar farm5abandoned3.7
Kenly Wind Farmwind farm12.3approved, not built5.8
Gathercauldwind farm15.6refused8.7
Land to the North West of Sypsies Farmsolar farm5abandoned8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2721, -2.7898).