Lingo Wind Farm (12.5 MW)
Lingo Wind Farm is a 12.5 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 4 October 2013; the record was last updated on 8 October 2013.
12.5 MWwind farm
refused on appealstatus in REPD
8 October 2013record last updated
Fifecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 23 January 2012 | Application submitted |
| 31 January 2013 | Refused by the planning authority |
| 4 October 2013 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 12.5 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 8 October 2013
- Operator or applicant
- Lingo Wind Energy Ltd
- Planning authority
- Fife
- Planning application reference
- 12/00129/EIA
- Appeal reference
- PPA-250-2153
- Turbines
- 5
- Address (REPD)
- Lingo Farm, Lingo, Fife
- Council area (by location)
- Fife
- Time to decision
- 53 weeks
- REPD reference
- 3844
Who decides
| Applications | Fife | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 91 | 10,236 |
| Refused | 17 (19%) | 19% |
| Solar refused | 0 of 36 | 12% |
| Onshore wind refused | 16 of 30 | 45% |
| Battery storage refused | 1 of 25 | 16% |
| Median time from submission to decision | 24.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Cameron Reservoir | solar farm | 5 | abandoned | 3.7 |
| Kenly Wind Farm | wind farm | 12.3 | approved, not built | 5.8 |
| Gathercauld | wind farm | 15.6 | refused | 8.7 |
| Land to the North West of Sypsies Farm | solar farm | 5 | abandoned | 8.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2721, -2.7898).