Energy Projects Near You

Kenly Wind Farm (12.3 MW)

Kenly Wind Farm is a 12.3 MW wind farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 August 2016, not yet built; the record was last updated on 21 September 2020. REPD also records that the planning permission expired on 26 October 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.3 MWwind farm
approved, not builtmay be out of datestatus in REPD
21 September 2020record last updated
Fifecouncil area

REPD also records that the planning permission expired on 26 October 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
22 April 2016Application submitted
25 August 2016Planning permission granted
26 October 2024Permission expired

Project details

Technology
wind farm
Capacity
12.3 MW
Status (REPD)
approved, not built
Record last updated
21 September 2020
Operator or applicant
University of St Andrews
Planning authority
Fife
Planning application reference
16/01425/EIA
Turbines
6
Turbine height
100 m
Address (REPD)
Kenly Farm, Boarhills, St. Andrews,
Council area (by location)
Fife
Time to decision
18 weeks
REPD reference
6082

Earlier applications for this site

ApplicationMWSubmittedOutcome
Kenly Wind Farm (University of St Andrew's) 11/02799/EIA13.820 June 2011refused 1 October 2012

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lingo Wind Farmwind farm12.5refused on appeal5.8
Land to the North West of Sypsies Farmsolar farm5abandoned7.2
Cameron Reservoirsolar farm5abandoned8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3098, -2.725).