Land to the North West of Sypsies Farm (5 MW solar farm)

Land to the North West of Sypsies Farm is a 5 MW solar farm project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 29 August 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
29 August 2018record last updated
Fifecouncil area

Planning timeline

DateStage
28 May 2015Application submitted
9 September 2015Planning permission granted
9 September 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
29 August 2018
Operator or applicant
RF Logan & Co
Planning authority
Fife
Planning application reference
15/00525/FULL
Site area
10.0 ha
Address (REPD)
Land To The North West Of Farm, Sypsies, Crail, Anstruther
Council area (by location)
Fife
Time to decision
15 weeks
REPD reference
5570

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kenly Wind Farmwind farm12.3approved, not built7.2
Lingo Wind Farmwind farm12.5refused on appeal8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.2612, -2.6489).