Energy Projects Near You

Solar, wind and battery projects near St Andrews (KY16)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KY16 (Fife): 4 approved but not yet running, 1 operational. The largest live scheme is Kenly Wind Farm (12.3 MW wind farm, approved on 25 August 2016, not yet built; REPD status may be out of date), 7.1 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Levenmouth demonstration turbine (Fife Energy Park) (7 MW, operational), 21.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
4approved, not running
1operational

Projects within 10 km of KY16

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Eden Campussolar farmsolar farm1operationalupdated Jun 2023Nov 2019granted Mar 2021Jun 2023Fife4.8
Cameron Reservoirsolar farmsolar farm5abandonedupdated Sep 2018Apr 2015granted Oct 2015Sep 2018Fife6.8
Kenly Wind Farmwind farmwind farm12.3approved, not built may be out of dateupdated Sep 2020Apr 2016granted Aug 2016Sep 2020Fife7.1
Lingo Wind Farmwind farmwind farm12.5refused on appealupdated Oct 2013Jan 2012refused Jan 2013Oct 2013Fife8.1
South Cassingraywind farmwind farm4.6refused on appealupdated Jan 2012Jul 2010refused Dec 2011Jan 2012Fife9.6
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Former Madras College, Kilrymont Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2024Nov 2023granted Jan 2024Feb 2024Fife2.6
Priorletham Farmhousesolar farmsolar farm0.2approved, not builtupdated Nov 2024Sep 2024granted Oct 2024Nov 2024Fife4.0
Clayton Caravan Park , Clayton Solar Panel Arraysolar farmsolar farm0.3approved, not builtupdated Jan 2024Dec 2023granted Jan 2024Jan 2024Fife6.2

Distance from the average position of the KY16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm402100.5
Rooftop solar101000.2
Wind farm3010212.3

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Levenmouth demonstration turbine (Fife Energy Park)7operationalupdated Nov 201821.9
Forthwind20approved, not builtupdated Aug 202323.4
Neart na Gaoithe450operationalupdated Mar 202636.3

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Fife decides solar, wind and battery applications

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in Fife

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KY16, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.