Energy Projects Near You

Solar, wind and battery projects near Cupar (KY15)

12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KY15 (Fife): 3 are waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is Solar Panels & BESS (49.9 MW solar farm, application submitted on 2 April 2025, no decision recorded), 2.0 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Forthwind (20 MW, approved, not built), 16.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12projects within 10 km
3awaiting a decision
2approved, not running
1operational

Projects within 10 km of KY15

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Uthrogle Mills Solar Farmsolar farmsolar farm3.5approved, not builtupdated Aug 2023Apr 2023granted Aug 2023Aug 2023Fife1.1
Solar Panels & BESSsolar farmsolar farm49.9application submittedupdated Jun 2025Apr 2025—Jun 2025Fife2.0
Solar Panels & BESSbattery storagebattery storage35application submittedupdated Jun 2025Apr 2025—Jun 2025Fife2.0
Fife Tractors, Drum Roadbattery storagebattery storage12.5refusedupdated Nov 2025Jun 2024refused Oct 2025Nov 2025Fife2.1
Ferrymuirbattery storagebattery storage49.9under constructionupdated Jul 2022Sep 2019granted Jan 2020Jul 2022Fife2.3
Over Rankeilour Farm Solar Farmsolar farmsolar farm29.9application submittedupdated Jun 2025May 2025—Jun 2025Fife2.7
Clatto Farm Turbineswind farmwind farm6refused on appealupdated Dec 2012May 2010refused Apr 2012Dec 2012Fife5.9
Devon Woodwind farmwind farm12.5refused on appealupdated Dec 2012Jun 2010refused Apr 2012Dec 2012Fife6.6
Clattowind farmwind farm30refusedupdated Nov 2015Sep 2003refused Nov 2004Nov 2015Fife7.3
Gathercauldwind farmwind farm15.6refusedupdated Dec 2009Jun 2007refused Jun 2009Dec 2009Fife8.2
Auchtermuchty Wind Farmwind farmwind farm10refusedupdated Jun 2010Jun 2006refused Jan 2008Jun 2010Fife9.7
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cupar Wastewater Treatment Works Solar Farmsolar farmsolar farm0.6operationalupdated Nov 2021Oct 2020granted Jan 2021Nov 2021Fife4.7

Distance from the average position of the KY15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4211083.3
Wind farm500050
Battery storage3110184.9

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Forthwind20approved, not builtupdated Aug 202316.4
Levenmouth demonstration turbine (Fife Energy Park)7operationalupdated Nov 201816.5

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Fife decides solar, wind and battery applications

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in Fife

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.