Fife Tractors, Drum Road (12.5 MW battery storage)

Fife Tractors, Drum Road is a 12.5 MW battery storage project in Fife, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 6 October 2025; the record was last updated on 7 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.5 MWbattery storage
refusedstatus in REPD
7 November 2025record last updated
Fifecouncil area

Planning timeline

DateStage
12 June 2024Application submitted
6 October 2025Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
12.5 MW
Status (REPD)
refused
Record last updated
7 November 2025
Operator or applicant
Downing Renewable Developments
Planning authority
Fife
Planning application reference
24/01082/FULL
Address (REPD)
200m To The W/O Fife Tractors Limited, Drum Road, Cupar
Council area (by location)
Fife
Time to decision
69 weeks
Name in REPD
Fife Tractors, Drum Road - Battery Energy Storage
REPD reference
16664

Who decides

ApplicationsFifeUK
Decided applications (solar, wind, battery)9110,236
Refused17 (19%)19%
Solar refused0 of 3612%
Onshore wind refused16 of 3045%
Battery storage refused1 of 2516%
Median time from submission to decision24.0 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ferrymuirbattery storage49.9under construction0.8
Over Rankeilour Farm Solar Farmsolar farm29.9application submitted1.6
Solar Panels & BESSsolar farm49.9application submitted3.7
Clatto Farm Turbineswind farm6refused on appeal7.7
Gathercauldwind farm15.6refused8.0
Devon Woodwind farm12.5refused on appeal8.3
Clattowind farm30refused9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.3147, -3.0376).