Neart na Gaoithe offshore wind farm

Neart na Gaoithe is a 450 MW offshore wind farm with 54 turbines in Scottish waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 July 2025; the record was last updated on 23 March 2026. Its REPD grid reference is 21 km from the nearest postcode on land (KY10 3XN, Fife). As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

450 MWoffshore wind farm
operationalstatus in REPD
23 March 2026record last updated
21 km from land (Fife)REPD location

Consent timeline

DateStage
30 July 2012Application submitted
16 May 2017Marine licence and Section 36 consent granted (Scottish Ministers)
1 January 2020Construction started
1 July 2025Operational

Project details

Technology
offshore wind farm
Capacity
450 MW
Turbines
54
Turbine capacity
8 MW
Turbine height
208 m
Status (REPD)
operational
Record last updated
23 March 2026
Operator or applicant
EDF Renewables Power
Consenting authority (REPD)
Marine Scotland
Application reference
not recorded
Nearest postcode on land
KY10 3XN (Fife), 21.4 km from the REPD grid reference
Time to decision
250 weeks
Contracts for Difference
AR1
REPD reference
2522

Who decides

As an offshore wind farm in Scottish waters, it is consented by Scottish Ministers; REPD names Marine Scotland as the consenting authority.

Postcode districts within 40 km

Districtkm
Anstruther (KY10)28.2
Dunbar (EH42)35.2
St Andrews (KY16)36.3
Elie (KY9)36.7
Cockburnspath (TD13)38.5
Carnoustie (DD7)38.9
North Berwick (EH39)38.9

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Inch Cape1,080under construction25.8

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (56.27, -2.25).