Inch Cape off Angus (applicant Red Rock Power, ICOL): 72 turbines of 15 MW, each 291 m tall. No neighbouring station has more powerful or taller machines. The site's REPD point sits about 22 km from the nearest postcode, DD11 5SG, near Arbroath (DD11).
Eight years between consent and construction
The application went in on 4 July 2013. The REPD dates the marine licence and the Section 36 consent to 16 May 2017, with Marine Scotland as the authority. That was the day the Court of Session reinstated the ministers' consents, which the RSPB had challenged. On the register's numbers that comes to 202 weeks against a median of 56.6 for offshore wind in Scottish waters. Construction only began on 16 June 2025; the project holds a Contract for Difference from round AR6.
The neighbours near Angus
At 22.5 km, Seagreen is operational at 1,075 MW, and in the same spot Seagreen Phase 1A at 540 MW is approved, not built. At 25.8 km, Neart na Gaoithe is operational at 450 MW. At 1,080 MW, Inch Cape is bigger than any of them. Record last updated on 8 June 2026, shortly before the extract for July 2026.