Energy Projects Near You

Solar, wind and battery projects near Montrose (DD10)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DD10 (Angus): 5 approved but not yet running, 3 operational. The largest live scheme is Balwyllo Farm, Dun Energy Storage Facility (50 MW battery storage, approved on 13 March 2024, not yet built), 8.7 km away. Offshore, 3 wind farms are recorded within 40 km; the nearest is Inch Cape (1,080 MW, under construction), 31.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
0awaiting a decision
5approved, not running
3operational

Projects within 10 km of DD10

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Glaxo Smith Kline Wind Turbinewind farmwind farm5refusedupdated Sep 2012Dec 2011refused Aug 2012Sep 2012Angus5.2
East Ballochysolar farmsolar farm39.9approved, not built may be out of dateupdated Mar 2020Jan 2020granted Sep 2020Mar 2020Angus7.0
East Ballochybattery storagebattery storage10approved, not built may be out of dateupdated Sep 2020Jan 2020granted Sep 2020Sep 2020Angus7.0
Brotherton (formerly Paul Matthew Hill wind turbines)wind farmwind farm4.6operationalupdated Jul 2017Apr 2013granted Jul 2014Jul 2017Aberdeenshire7.9
Dunmill, Substation Dunbattery storagebattery storage49.9approved, not builtupdated Nov 2025Jan 2024granted Aug 2024Nov 2025Angus8.6
Balwyllo Farm, Dun Energy Storage Facilitybattery storagebattery storage50approved, not builtupdated Jul 2024Oct 2023granted Mar 2024Jul 2024Angus8.7
Tullo Wind Farm South (Ext.)wind farmwind farm10operationalupdated Nov 2014Nov 2011granted Sep 2012Nov 2014Aberdeenshire8.7
Hill of Garvock Wind Energy Projectwind farmwind farm15application withdrawnupdated Oct 2005Jun 2003—Oct 2005Aberdeenshire8.9
Hill of Garvock Wind Energy Project (2)wind farmwind farm15refusedupdated May 2006Apr 2004refused Oct 2004May 2006Aberdeenshire8.9
Easter Tulloch Wind Farm (Tullo Extension)wind farmwind farm25operationalupdated Sep 2014Aug 2011granted Sep 2012Sep 2014Aberdeenshire9.8
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Baker Hughes, Charleton Roadrooftop solarrooftop solar0.7approved, not builtupdated May 2026Mar 2026granted Apr 2026May 2026Angus3.3

Distance from the average position of the DD10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1010039.9
Rooftop solar101000.7
Wind farm600320
Battery storage30300110

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Inch Cape1,080under constructionupdated Jun 202631.0
Seagreen1,075operationalupdated Oct 202333.0
Seagreen Phase 1A540approved, not builtupdated Jul 202333.0

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Angus decides solar, wind and battery applications

ApplicationsAngusUK
Decided applications (solar, wind, battery)7210,236
Refused21 (29%)19%
Solar refused1 of 3612%
Onshore wind refused18 of 1945%
Battery storage refused2 of 1716%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

All projects in Angus

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DD10, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.