Energy Projects Near You

Solar, wind and battery projects near Laurencekirk (AB30)

21 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB30 (Aberdeenshire): 4 are waiting for a planning decision, 4 approved but not yet running, 6 operational. The largest live scheme is Droop Hill, Glenbervie Solar Park (3.1 MW solar farm, application submitted on 30 May 2025, no decision recorded), 9.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21projects within 10 km
4awaiting a decision
4approved, not running
6operational

Projects within 10 km of AB30

Projects of 1 MW and more (16)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hill of Garvock Wind Energy Projectwind farmwind farm15application withdrawnupdated Oct 2005Jun 2003—Oct 2005Aberdeenshire3.0
Hill of Garvock Wind Energy Project (2)wind farmwind farm15refusedupdated May 2006Apr 2004refused Oct 2004May 2006Aberdeenshire3.0
Tullo Wind Farm North Extension (Shiels Wind Farm)wind farmwind farm7.5operationalupdated Mar 2014Jul 2011granted Feb 2012Mar 2014Aberdeenshire4.1
Tullo Wind Farm South (Ext.)wind farmwind farm10operationalupdated Nov 2014Nov 2011granted Sep 2012Nov 2014Aberdeenshire4.9
Easter Tulloch Wind Farm (Tullo Extension)wind farmwind farm25operationalupdated Sep 2014Aug 2011granted Sep 2012Sep 2014Aberdeenshire5.1
Bogmuir Farm Wind Turbinewind farmwind farm1application withdrawnupdated Jul 2013Oct 2012—Jul 2013Aberdeenshire5.8
Brownieleys - 3 Wind Turbineswind farmwind farm7.5operationalupdated Feb 2017Apr 2012granted Oct 2013Feb 2017Aberdeenshire6.1
Fordoun Sawmill Solar Arraysolar farmsolar farm1.5approved, not builtupdated Oct 2024Jan 2021granted May 2021Oct 2024Aberdeenshire6.2
HydroGlen Project - Glensaugh Farmwind turbinewind turbine1under constructionupdated Feb 2025Feb 2024granted Apr 2024Feb 2025Aberdeenshire6.3
Brotherton (formerly Paul Matthew Hill wind turbines)wind farmwind farm4.6operationalupdated Jul 2017Apr 2013granted Jul 2014Jul 2017Aberdeenshire7.4
Herscha Wind energy Project (Extension)wind farmwind farm1.6permission expiredupdated Sep 2020Mar 2013granted May 2015Sep 2020Aberdeenshire7.5
Greenleyswind farmwind farm1.7application withdrawnupdated Jul 2015Jun 2014—Jul 2015Aberdeenshire7.8
Boy's Hill Wind Clusterwind farmwind farm6.9refusedupdated Feb 2014Jan 2013refused Oct 2013Feb 2014Aberdeenshire8.3
Droop Hill, Glenbervie Solar Parksolar farmsolar farm3.1application submittedupdated Jul 2025May 2025—Jul 2025Aberdeenshire9.6
Droop Hill Wind Farm xwind farmwind farm4.6operationalupdated Apr 2016May 2009granted Apr 2013Apr 2016Aberdeenshire9.7
Droop Hill Wind Farmwind farmwind farm3.9application withdrawnupdated Jul 2013Aug 2006—Jul 2013Aberdeenshire10.0
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Mains Of Haulkertonrooftop solarrooftop solar0.1approved, not built may be out of dateupdated May 2022May 2022granted Jun 2022May 2022Aberdeenshire0.3
Blackiemuirsolar farmsolar farm0.2approved, not built may be out of dateupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Aberdeenshire1.7
HydroGlen Project - Glensaugh Farmsolar farmsolar farm0.2application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Aberdeenshire6.3
HydroGlen Project - Glensaugh Farmbattery storagebattery storage—application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Aberdeenshire6.6
Castleton Farm Shopsolar farmsolar farm0.2application submittedMay 2026——Aberdeenshire7.5

Distance from the average position of the AB30 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm532005.2
Rooftop solar101000.1
Wind farm1300620
Wind turbine101001
Battery storage110000

MW in pipeline: pending, approved and under-construction capacity.

How Aberdeenshire decides solar, wind and battery applications

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

All projects in Aberdeenshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near AB30, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.