Energy Projects Near You

Solar, wind and battery projects near Stonehaven (AB39)

15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AB39 (Aberdeenshire): 2 are waiting for a planning decision, 6 approved but not yet running, 3 operational. The largest live scheme is Old Schoolhouse, Barras (49.9 MW battery storage, application submitted on 9 January 2025, no decision recorded), 8.2 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Kincardine Offshore Windfarm (49.5 MW, operational), 20.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects within 10 km
2awaiting a decision
6approved, not running
3operational

Projects within 10 km of AB39

Projects of 1 MW and more (13)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Craigneil Hillwind farmwind farm35approved, not builtupdated Aug 2025May 2018granted Sep 2022Aug 2025Aberdeenshire1.4
Kempstone Hill Wind Turbineswind farmwind farm2.4application withdrawnupdated Apr 2013Aug 2012—Apr 2013Aberdeenshire2.0
Tullo Farmwind farmwind farm17.5operationalupdated Oct 2010Oct 2003granted Jun 2004Oct 2010Aberdeenshire2.1
Meikle Carewewind farmwind farm10operationalupdated Jun 2014Nov 2006granted May 2010Jun 2014Aberdeenshire5.6
Brucklaywaird Wind Farmwind farmwind farm6.9refusedupdated May 2015Feb 2014refused Apr 2015May 2015Aberdeenshire6.4
Muchalls Jnct, Muchallssolar farmsolar farm6.1application withdrawnupdated Dec 2025Jun 2025—Dec 2025Aberdeenshire6.8
Clochnahill Wind Farmwind farmwind farm5.2operationalupdated Feb 2013Jul 2006granted Aug 2009Feb 2013Aberdeenshire7.1
Clochnahill Windfarmwind farmwind farm6refusedupdated Nov 2007May 2006refused Mar 2007Nov 2007Aberdeenshire7.3
Old Schoolhouse, Barrasbattery storagebattery storage49.9application submittedupdated Jan 2025Jan 2025—Jan 2025Aberdeenshire8.2
Fetteresso Wind Farm (Mid Hill 3)wind farmwind farm42approved, not builtupdated Oct 2022Jun 2019granted Sep 2022Oct 2022Aberdeenshire8.3
Meetlaw Farm, Fordounbattery storagebattery storage49.9approved, not builtupdated Oct 2023Jan 2023granted Sep 2023Oct 2023Aberdeenshire8.3
West Bendingsbattery storagebattery storage30approved, not builtupdated Apr 2022Sep 2022granted Jun 2023Apr 2022Aberdeenshire8.4
Forest Avenue Cottage, Drumlithiebattery storagebattery storage49.9approved, not builtupdated Nov 2023May 2023granted Nov 2023Nov 2023Aberdeenshire10.0
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ferniebrae Barraswind turbinewind turbine0.3approved, not builtupdated Feb 2026Dec 2024granted Dec 2025Feb 2026Aberdeenshire8.5
Brigstanes Farm, Catterlinewind farmwind farm—application submittedMay 2026——Aberdeenshire9.0

Distance from the average position of the AB39 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100000
Wind farm9123277
Wind turbine101000.3
Battery storage41300180

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Kincardine Offshore Windfarm49.5operationalupdated Mar 202220.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Aberdeenshire decides solar, wind and battery applications

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

All projects in Aberdeenshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.