Meikle Carewe (10 MW wind farm)

Meikle Carewe is a 10 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 July 2013; the record was last updated on 24 June 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
operationalstatus in REPD
24 June 2014record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
29 November 2006Application submitted
20 May 2010Planning permission granted
26 July 2012Construction started
30 July 2013Operational

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
24 June 2014
Operator or applicant
The Renewables Infrastructure Group (TRIG)
Planning authority
Aberdeenshire
Planning application reference
APP/2006/3934
Appeal reference
PPA-110-2053
Turbines
12
Address (REPD)
Rickarton Farms, Stonehaven,
Council area (by location)
Aberdeenshire
Time to decision
181 weeks
REPD reference
4109

Earlier applications for this site

ApplicationMWSubmittedOutcome
Meikle Carewe S000295PF1420 March 2000refused 4 December 2001

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Craigneil Hillwind farm35approved, not built5.8
Tullo Farmwind farm17.5operational7.4
Fetteresso Wind Farm (Mid Hill 3)wind farm42approved, not built7.4
Muchalls Jnct, Muchallssolar farm6.1application withdrawn7.9
Brucklaywaird Wind Farmwind farm6.9refused8.4
Clochnahill Windfarmwind farm6refused9.2
Clochnahill Wind Farmwind farm5.2operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.0188, -2.2783).