Energy Projects Near You

Craigneil Hill (35 MW wind farm)

Craigneil Hill is a 35 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 September 2022, not yet built; the record was last updated on 4 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWwind farm
approved, not builtstatus in REPD
4 August 2025record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
1 May 2018Application submitted
3 September 2021Refused by the planning authority
23 December 2021Appeal lodged
29 September 2022Planning permission granted
29 September 2022Appeal allowed
29 September 2027Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
4 August 2025
Operator or applicant
ESB Asset Development UK
Planning authority
Aberdeenshire
Planning application reference
APP/2018/0993
Appeal reference
PPA-110-2420
Turbines
11
Turbine height
135 m
Address (REPD)
Land To The North And North East Of Hillside, Rickarton, Stonehaven
Council area (by location)
Aberdeenshire
Time to decision
230 weeks
REPD reference
6259

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tullo Farmwind farm17.5operational1.6
Brucklaywaird Wind Farmwind farm6.9refused5.1
Clochnahill Wind Farmwind farm5.2operational5.8
Meikle Carewewind farm10operational5.8
Clochnahill Windfarmwind farm6refused6.0
Old Schoolhouse, Barrasbattery storage49.9application submitted6.9
Meetlaw Farm, Fordounbattery storage49.9approved, not built7.0
West Bendingsbattery storage30approved, not built7.0
Fetteresso Wind Farm (Mid Hill 3)wind farm42approved, not built7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.9734, -2.2303).