Energy Projects Near You

Fetteresso Wind Farm (Mid Hill 3) (42 MW)

Fetteresso Wind Farm (Mid Hill 3) is a 42 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 September 2022, not yet built; the record was last updated on 19 October 2022. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42 MWwind farm
approved, not builtstatus in REPD
19 October 2022record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
3 June 2019Application submitted
21 September 2022Section 36 consent granted (Scottish Ministers)
21 September 2028Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
42 MW
Status (REPD)
approved, not built
Record last updated
19 October 2022
Operator or applicant
Fred Olsen Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00001851
Turbines
10
Turbine height
200 m
Address (REPD)
Fetteresso, Stonehaven
Council area (by location)
Aberdeenshire
Time to decision
172 weeks
REPD reference
6577

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Jacksbank Wind Farm (Glenbervie)wind farm6.8operational3.6
Brucklaywaird Wind Farmwind farm6.9refused4.0
Clochnahill Windfarmwind farm6refused4.0
Forest Avenue Cottage, Drumlithiebattery storage49.9approved, not built4.0
Meetlaw Farm, Fordounbattery storage49.9approved, not built4.7
Clochnahill Wind Farmwind farm5.2operational4.9
Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagesolar farm9.2approved, not built5.2
West Bendingsbattery storage30approved, not built5.2
Old Schoolhouse, Barrasbattery storage49.9application submitted6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.9644, -2.3474).