Clochnahill Wind Farm (5.2 MW)

Clochnahill Wind Farm is a 5.2 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 January 2012; the record was last updated on 26 February 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.2 MWwind farm
operationalstatus in REPD
26 February 2013record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
27 July 2006Application submitted
5 August 2009Planning permission granted
20 January 2012Operational

Project details

Technology
wind farm
Capacity
5.2 MW
Status (REPD)
operational
Record last updated
26 February 2013
Operator or applicant
Private Developer
Planning authority
Aberdeenshire
Planning application reference
not recorded
Turbines
4
Address (REPD)
Clochnahill, Stonehaven AB39 2XY
Council area (by location)
Aberdeenshire
Time to decision
158 weeks
REPD reference
2839

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clochnahill Windfarmwind farm6refused0.9
Brucklaywaird Wind Farmwind farm6.9refused1.1
Meetlaw Farm, Fordounbattery storage49.9approved, not built1.3
West Bendingsbattery storage30approved, not built1.3
Old Schoolhouse, Barrasbattery storage49.9application submitted2.0
Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagesolar farm9.2approved, not built3.2
Forest Avenue Cottage, Drumlithiebattery storage49.9approved, not built3.4
Bridgend Farm, Arbuthnottbattery storage49.9approved, not built3.8
St John Hillwind farm7.7operational4.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.9335, -2.2906).