Energy Projects Near You

Bridgend Farm, Arbuthnott (49.9 MW battery storage)

Bridgend Farm, Arbuthnott is a 49.9 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 September 2025, not yet built; the record was last updated on 28 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
28 October 2025record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
13 February 2025Application submitted
16 September 2025Planning permission granted
16 September 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
28 October 2025
Operator or applicant
OPDE UK Limted
Planning authority
Aberdeenshire
Planning application reference
APP/2025/0089
Address (REPD)
Bridgend Farm Arbuthnott
Council area (by location)
Aberdeenshire
Time to decision
31 weeks
Name in REPD
Bridgend Farm, Arbuthnott - Battery Energy Storage System
REPD reference
16522

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagesolar farm9.2approved, not built1.8
West Bendingsbattery storage30approved, not built2.6
Meetlaw Farm, Fordounbattery storage49.9approved, not built2.8
Forest Avenue Cottage, Drumlithiebattery storage49.9approved, not built3.1
Old Schoolhouse, Barrasbattery storage49.9application submitted3.1
St John Hillwind farm7.7operational3.2
St. Johns Hillwind farm7.7operational3.5
Clochnahill Wind Farmwind farm5.2operational3.8
Clochnahill Windfarmwind farm6refused3.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.9036, -2.3223).