St. Johns Hill (7.7 MW wind farm)
St. Johns Hill is a 7.7 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2013; the record was last updated on 6 March 2014.
7.7 MWwind farm
operationalstatus in REPD
6 March 2014record last updated
Aberdeenshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 22 December 2004 | Application submitted |
| 11 October 2006 | Refused by the planning authority |
| 26 November 2007 | Planning permission granted |
| 26 November 2007 | Appeal allowed |
| 1 April 2013 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 7.7 MW
- Status (REPD)
- operational
- Record last updated
- 6 March 2014
- Operator or applicant
- K E Projects AF
- Planning authority
- Aberdeenshire
- Planning application reference
- 2004/4666
- Turbines
- 9
- Address (REPD)
- Chapel of Barras nr Kinneff, South of Stonehaven
- Council area (by location)
- Aberdeenshire
- Time to decision
- 153 weeks
- REPD reference
- 4031
Who decides
| Applications | Aberdeenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 200 | 10,236 |
| Refused | 64 (32%) | 19% |
| Solar refused | 1 of 40 | 12% |
| Onshore wind refused | 60 of 132 | 45% |
| Battery storage refused | 3 of 28 | 16% |
| Median time from submission to decision | 40.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 15 / 13 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| St John Hill | wind farm | 7.7 | operational | 0.6 |
| Old Schoolhouse, Barras | battery storage | 49.9 | application submitted | 3.2 |
| Bridgend Farm, Arbuthnott | battery storage | 49.9 | approved, not built | 3.5 |
| West Bendings | battery storage | 30 | approved, not built | 4.4 |
| Meetlaw Farm, Fordoun | battery storage | 49.9 | approved, not built | 4.9 |
| Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storage | solar farm | 9.2 | approved, not built | 5.1 |
| Clochnahill Wind Farm | wind farm | 5.2 | operational | 5.1 |
| Clochnahill Windfarm | wind farm | 6 | refused | 5.7 |
| Brucklaywaird Wind Farm | wind farm | 6.9 | refused | 6.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.8886, -2.2724).