St. Johns Hill (7.7 MW wind farm)

St. Johns Hill is a 7.7 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2013; the record was last updated on 6 March 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.7 MWwind farm
operationalstatus in REPD
6 March 2014record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
22 December 2004Application submitted
11 October 2006Refused by the planning authority
26 November 2007Planning permission granted
26 November 2007Appeal allowed
1 April 2013Operational

Project details

Technology
wind farm
Capacity
7.7 MW
Status (REPD)
operational
Record last updated
6 March 2014
Operator or applicant
K E Projects AF
Planning authority
Aberdeenshire
Planning application reference
2004/4666
Turbines
9
Address (REPD)
Chapel of Barras nr Kinneff, South of Stonehaven
Council area (by location)
Aberdeenshire
Time to decision
153 weeks
REPD reference
4031

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
St John Hillwind farm7.7operational0.6
Old Schoolhouse, Barrasbattery storage49.9application submitted3.2
Bridgend Farm, Arbuthnottbattery storage49.9approved, not built3.5
West Bendingsbattery storage30approved, not built4.4
Meetlaw Farm, Fordounbattery storage49.9approved, not built4.9
Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagesolar farm9.2approved, not built5.1
Clochnahill Wind Farmwind farm5.2operational5.1
Clochnahill Windfarmwind farm6refused5.7
Brucklaywaird Wind Farmwind farm6.9refused6.2