Energy Projects Near You

Brucklaywaird Wind Farm (6.9 MW)

Brucklaywaird Wind Farm is a 6.9 MW wind farm project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 30 April 2015; the record was last updated on 7 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
refusedstatus in REPD
7 May 2015record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
11 February 2014Application submitted
30 April 2015Refused by the planning authority

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
refused
Record last updated
7 May 2015
Operator or applicant
Blue Energy (Auquhirie Extension) Limited
Planning authority
Aberdeenshire
Planning application reference
APP/2014/0254
Turbines
3
Address (REPD)
Brucklaywaird Farm, Stonehaven AB39 3XD
Council area (by location)
Aberdeenshire
Time to decision
63 weeks
REPD reference
4287

Who decides

ApplicationsAberdeenshireUK
Decided applications (solar, wind, battery)20010,236
Refused64 (32%)19%
Solar refused1 of 4012%
Onshore wind refused60 of 13245%
Battery storage refused3 of 2816%
Median time from submission to decision40.6 weeks17.0 weeks
Appeals lodged / allowed15 / 13—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clochnahill Windfarmwind farm6refused0.9
Clochnahill Wind Farmwind farm5.2operational1.1
Meetlaw Farm, Fordounbattery storage49.9approved, not built2.0
West Bendingsbattery storage30approved, not built2.2
Old Schoolhouse, Barrasbattery storage49.9application submitted3.1
Forest Avenue Cottage, Drumlithiebattery storage49.9approved, not built3.6
Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagesolar farm9.2approved, not built3.8
Fetteresso Wind Farm (Mid Hill 3)wind farm42approved, not built4.0
Bridgend Farm, Arbuthnottbattery storage49.9approved, not built4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (56.9435, -2.2933).