Renewable energy projects in Aberdeenshire
251 solar, wind or battery projects of 150 kW or more are located in Aberdeenshire (REPD, July 2026 extract): 34 pending, 78 approved but not running, 69 operational and 39 refused. The council refused 64 of 200 decided applications (32%; UK 19%), with a median 41 weeks from submission to decision.
251projects in the council area
34awaiting a decision
78approved, not running
32%of decisions refused
How Aberdeenshire decides
| Applications | Aberdeenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 200 | 10,236 |
| Refused | 64 (32%) | 19% |
| Solar refused | 1 of 40 | 12% |
| Onshore wind refused | 60 of 132 | 45% |
| Battery storage refused | 3 of 28 | 16% |
| Median time from submission to decision | 40.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 15 / 13 | — |
Projects in Aberdeenshire
Projects of 1 MW and more (100)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Abbotshaugh Battery Storagebattery storage | battery storage | 500 | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 |
| Rothienorman, Middleton of Blackhillsbattery storage | battery storage | 500 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 |
| Greystone, Blackhillsbattery storage | battery storage | 500 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 |
| Flushing, Longsidebattery storage | battery storage | 400 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 |
| Netherton, Langside Roadbattery storage | battery storage | 400 | application submittedupdated Oct 2025 | Aug 2025 | — | Oct 2025 |
| Kintore Battery Energy Storage Projectbattery storage | battery storage | 300 | approved, not builtupdated Jul 2025 | Feb 2021 | granted May 2025 | Jul 2025 |
| Womblehill Farm, Kintorebattery storage | battery storage | 200 | application submittedupdated Oct 2025 | Jun 2025 | — | Oct 2025 |
| Salamander Offshore Wind Farm Battery Storage and Onshore Connectionbattery storage | battery storage | 180 | approved, not builtupdated Nov 2025 | Aug 2024 | granted Oct 2025 | Nov 2025 |
| Hill of Fare Wind Farmwind farm | wind farm | 150 | abandonedupdated Sep 2018 | — | — | Sep 2018 |
| Hill of Fare Wind Farm & Battery Storagewind farm | wind farm | 106 | application submitted may be out of dateupdated Nov 2023 | Nov 2023 | — | Nov 2023 |
| Kinmuck Battery Energy Storagebattery storage | battery storage | 105 | approved, not builtupdated Jul 2025 | Sep 2023 | granted May 2025 | Jul 2025 |
| Glendye Estatewind farm | wind farm | 104 | approved, not builtupdated Feb 2026 | Oct 2018 | granted Oct 2023 | Feb 2026 |
| Hill of Fare Wind Farm & Battery Storagebattery storage | battery storage | 100 | application submitted may be out of dateupdated Nov 2023 | Nov 2023 | — | Nov 2023 |
| Clashindarroch 2wind farm | wind farm | 77 | approved, not builtupdated Jun 2023 | Dec 2019 | granted Aug 2023 | Jun 2023 |
| Frodo Solar and Battery Energy Developmentsolar farm | solar farm | 60.1 | approved, not builtupdated Apr 2022 | Mar 2022 | granted May 2023 | Apr 2022 |
| Mid Hill Iwind farm | wind farm | 57.5 | operationalupdated Sep 2014 | Feb 2003 | granted Jun 2005 | Sep 2014 |
| Electricity Sub Station, Strichenbattery storage | battery storage | 50 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Mar 2022 | Dec 2021 |
| Frodo Solar and Battery Energy Developmentbattery storage | battery storage | 50 | approved, not builtupdated Apr 2022 | Mar 2022 | granted May 2023 | Apr 2022 |
| Greenbank Caravan & Trailers, Hillhead Of Phingaskbattery storage | battery storage | 50 | approved, not built may be out of dateupdated Feb 2023 | Sep 2022 | granted Jan 2023 | Feb 2023 |
| Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm | solar farm | 50 | approved, not builtupdated Mar 2023 | Feb 2021 | granted Dec 2022 | Mar 2023 |
| Clashindarroch Wind Farm Extensionbattery storage | battery storage | 50 | approved, not builtupdated Jan 2026 | Jan 2023 | granted Dec 2025 | Jan 2026 |
| Kintoresolar farm | solar farm | 50 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 |
| Fordtown Energy Storagebattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated May 2022 | Sep 2020 | granted Feb 2021 | May 2022 |
| Rothienormanbattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Feb 2022 | Jun 2022 | granted Nov 2022 | Feb 2022 |
| Law Of Doune Road, Macduffbattery storage | battery storage | 49.9 | approved, not builtupdated Dec 2023 | Feb 2023 | granted Dec 2023 | Dec 2023 |
| South Leylodge Farmhouse, Kintorebattery storage | battery storage | 49.9 | approved, not builtupdated May 2024 | Sep 2022 | granted Apr 2023 | May 2024 |
| Overhill Farm, Rothienormanbattery storage | battery storage | 49.9 | under constructionupdated Sep 2025 | Nov 2022 | granted Mar 2023 | Sep 2025 |
| Meetlaw Farm, Fordounbattery storage | battery storage | 49.9 | approved, not builtupdated Oct 2023 | Jan 2023 | granted Sep 2023 | Oct 2023 |
| Forest Avenue Cottage, Drumlithiebattery storage | battery storage | 49.9 | approved, not builtupdated Nov 2023 | May 2023 | granted Nov 2023 | Nov 2023 |
| Old Schoolhouse, Barrasbattery storage | battery storage | 49.9 | application submittedupdated Jan 2025 | Jan 2025 | — | Jan 2025 |
| Kintore Substation, Leylodgebattery storage | battery storage | 49.9 | approved, not builtupdated Oct 2024 | Dec 2023 | granted Sep 2024 | Oct 2024 |
| Bridgend Farm, Arbuthnottbattery storage | battery storage | 49.9 | approved, not builtupdated Oct 2025 | Feb 2025 | granted Sep 2025 | Oct 2025 |
| Smiddyhill, Strichenbattery storage | battery storage | 49.9 | application submittedupdated Dec 2024 | Oct 2024 | — | Dec 2024 |
| Fairfieldbattery storage | battery storage | 49.9 | refusedupdated Apr 2026 | Jul 2025 | refused Feb 2026 | Apr 2026 |
| Middleton Of Potterton Farmbattery storage | battery storage | 49.9 | approved, not builtupdated Jul 2025 | Jun 2024 | granted Jul 2025 | Jul 2025 |
| Whitestones Birks Farm, Longmanhillbattery storage | battery storage | 49.9 | refusedupdated Dec 2025 | Jun 2025 | refused Nov 2025 | Dec 2025 |
| Middleton Of Blackhills, Rothienormanbattery storage | battery storage | 49.9 | application submittedupdated Apr 2025 | Apr 2025 | — | Apr 2025 |
| Boothby Roadbattery storage | battery storage | 49.9 | application submittedupdated Dec 2025 | May 2025 | — | Dec 2025 |
| Broomhill BESSbattery storage | battery storage | 49 | approved, not built may be out of dateupdated Jun 2026 | Feb 2022 | granted Jul 2022 | Jun 2026 |
| A981 Fraserburghbattery storage | battery storage | 45 | approved, not builtupdated Jul 2023 | Feb 2023 | granted Apr 2023 | Jul 2023 |
| Fetteresso Wind Farm (Mid Hill 3)wind farm | wind farm | 42 | approved, not builtupdated Oct 2022 | Jun 2019 | granted Sep 2022 | Oct 2022 |
| Bilbo Solar Farm Energy Storagebattery storage | battery storage | 40 | under constructionupdated Feb 2025 | Jun 2019 | granted Oct 2019 | Feb 2025 |
| Kintorebattery storage | battery storage | 40 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 |
| Clashindarrochwind farm | wind farm | 37 | operationalupdated Jun 2015 | Jun 2009 | granted Dec 2010 | Jun 2015 |
| Bilbo Solar Farmsolar farm | solar farm | 36.6 | under constructionupdated Oct 2024 | Jun 2019 | granted Nov 2019 | Oct 2024 |
| Craigneil Hillwind farm | wind farm | 35 | approved, not builtupdated Aug 2025 | May 2018 | granted Sep 2022 | Aug 2025 |
| Brownside Farm - Electricity Production Facility & Battery Storagesolar farm | solar farm | 35 | approved, not builtupdated Feb 2026 | Sep 2024 | granted Jun 2025 | Feb 2026 |
| Stoneyhillwind farm | wind farm | 30.6 | application withdrawnupdated Jun 2005 | Dec 2002 | — | Jun 2005 |
| West Bendingsbattery storage | battery storage | 30 | approved, not builtupdated Apr 2022 | Sep 2022 | granted Jun 2023 | Apr 2022 |
| Mormond Hill Windfarmwind farm | wind farm | 27.6 | refused on appealupdated Aug 2015 | Nov 2011 | refused Nov 2014 | Aug 2015 |
| Glens of Foudlandwind farm | wind farm | 26 | operationalupdated Feb 2016 | Jan 2001 | granted Oct 2001 | Feb 2016 |
| Easter Tulloch Wind Farm (Tullo Extension)wind farm | wind farm | 25 | operationalupdated Sep 2014 | Aug 2011 | granted Sep 2012 | Sep 2014 |
| Fraserburgh Developmentbattery storage | battery storage | 25 | permission expiredupdated Jan 2020 | Mar 2018 | granted May 2018 | Jan 2020 |
| Strichen Northbattery storage | battery storage | 25 | abandonedupdated Aug 2021 | Mar 2018 | — | Aug 2021 |
| Denheadsolar farm | solar farm | 25 | approved, not builtupdated Apr 2026 | Nov 2023 | granted Apr 2024 | Apr 2026 |
| Hill of Snowy Slackwind farm | wind farm | 22 | application withdrawnupdated May 2006 | Jan 2005 | — | May 2006 |
| Kincraig Solar Farm and battery storage systemsolar farm | solar farm | 21 | under constructionupdated Jun 2025 | Apr 2022 | granted Oct 2022 | Jun 2025 |
| Hill of Bracowind farm | wind farm | 20 | application withdrawnupdated Sep 2013 | Feb 2013 | — | Sep 2013 |
| Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitybattery storage | battery storage | 20 | approved, not builtupdated Mar 2023 | Feb 2021 | granted Dec 2022 | Mar 2023 |
| Kildrummy Windfarmwind farm | wind farm | 18.4 | operationalupdated Jun 2014 | Dec 2006 | granted Aug 2009 | Jun 2014 |
| Mid Hill - Phase IIwind farm | wind farm | 18.4 | operationalupdated Feb 2016 | Feb 2003 | granted Jun 2005 | Feb 2016 |
| Tibberchindy Wind Farmwind farm | wind farm | 18 | refusedupdated Mar 2014 | Oct 2012 | refused Feb 2014 | Mar 2014 |
| Stony Hillwind farm | wind farm | 18 | application withdrawnupdated Jul 2015 | Jul 2013 | — | Jul 2015 |
| Tullo Farmwind farm | wind farm | 17.5 | operationalupdated Oct 2010 | Oct 2003 | granted Jun 2004 | Oct 2010 |
| Boyndie Airfieldwind farm | wind farm | 16.7 | operationalupdated Jun 2016 | Jun 2003 | granted Jul 2004 | Jun 2016 |
| Pressendyewind farm | wind farm | 16.1 | refused on appealupdated Dec 2010 | Feb 2008 | refused Jul 2016 | Dec 2010 |
| Hill of Garvock Wind Energy Projectwind farm | wind farm | 15 | application withdrawnupdated Oct 2005 | Jun 2003 | — | Oct 2005 |
| Hill of Garvock Wind Energy Project (2)wind farm | wind farm | 15 | refusedupdated May 2006 | Apr 2004 | refused Oct 2004 | May 2006 |
| Brownside Farm - Electricity Production Facility & Battery Storagebattery storage | battery storage | 14.9 | approved, not builtupdated Feb 2026 | Sep 2024 | granted Jun 2025 | Feb 2026 |
| Hill of Stoneyfieldwind farm | wind farm | 14.4 | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 |
| Hillhead Of Gask, Longhavensolar farm | solar farm | 14.2 | under constructionupdated Feb 2026 | Jan 2022 | granted Apr 2022 | Feb 2026 |
| Glens of Foudland Wind Farm (Extension)wind farm | wind farm | 14 | application withdrawnupdated Mar 2015 | Aug 2015 | — | Mar 2015 |
| Cullerlie Solar Farmsolar farm | solar farm | 13 | approved, not builtupdated Nov 2021 | Feb 2021 | granted Nov 2021 | Nov 2021 |
| Gordonstown Hill Wind Farmwind farm | wind farm | 12.5 | operationalupdated Jun 2013 | Dec 2008 | granted Jul 2009 | Jun 2013 |
| Dummuiewind farm | wind farm | 12.3 | operationalupdated Jun 2015 | Aug 2003 | granted Feb 2004 | Jun 2015 |
| Methlick Farmers Wind Energy Projectwind farm | wind farm | 12 | operationalupdated Aug 2012 | Oct 2006 | granted Jul 2007 | Aug 2012 |
| Hill of Fishriewind farm | wind farm | 11.3 | refusedupdated Jan 2014 | Jul 2011 | refused Nov 2013 | Jan 2014 |
| Cloffrickford Farmwind farm | wind farm | 10 | application withdrawnupdated Jul 2009 | — | — | Jul 2009 |
| Meikle Carewewind farm | wind farm | 10 | operationalupdated Jun 2014 | Nov 2006 | granted May 2010 | Jun 2014 |
| Cairnborrowwind farm | wind farm | 10 | operationalupdated Apr 2018 | Oct 2013 | granted Aug 2014 | Apr 2018 |
| Tullo Wind Farm South (Ext.)wind farm | wind farm | 10 | operationalupdated Nov 2014 | Nov 2011 | granted Sep 2012 | Nov 2014 |
| Strichen Southbattery storage | battery storage | 10 | abandonedupdated Jan 2020 | Mar 2018 | — | Jan 2020 |
| Whitestones, Cuminestown Solar Farmsolar farm | solar farm | 9.9 | approved, not builtupdated Feb 2026 | Apr 2025 | granted Jul 2025 | Feb 2026 |
| Hill of Tillymorgan (Kirkton Farm) Wind turbineswind farm | wind farm | 9.6 | operationalupdated Apr 2017 | Mar 2011 | granted Apr 2013 | Apr 2017 |
| Cloffrickfordwind farm | wind farm | 9.2 | application withdrawnupdated Jun 2010 | Feb 2010 | — | Jun 2010 |
| Mains of Cairnbrogiewind farm | wind farm | 9.2 | refused on appealupdated Jun 2010 | Dec 2008 | refused Jun 2017 | Jun 2010 |
| Land at Overside and Greenwellheads Farmswind farm | wind farm | 9.2 | operationalupdated Dec 2013 | Mar 2011 | granted Sep 2011 | Dec 2013 |
| Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagesolar farm | solar farm | 9.2 | approved, not builtupdated Feb 2023 | Aug 2022 | granted Feb 2023 | Feb 2023 |
| St John Hillwind farm | wind farm | 7.7 | operationalupdated Aug 2013 | Jul 2008 | granted Dec 2009 | Aug 2013 |
| St. Johns Hillwind farm | wind farm | 7.7 | operationalupdated Mar 2014 | Dec 2004 | granted Nov 2007 | Mar 2014 |
| Tullo Wind Farm North Extension (Shiels Wind Farm)wind farm | wind farm | 7.5 | operationalupdated Mar 2014 | Jul 2011 | granted Feb 2012 | Mar 2014 |
| Brownieleys - 3 Wind Turbineswind farm | wind farm | 7.5 | operationalupdated Feb 2017 | Apr 2012 | granted Oct 2013 | Feb 2017 |
| Greenside Extensionwind farm | wind farm | 7 | approved, not builtupdated May 2025 | Mar 2024 | granted Mar 2025 | May 2025 |
| Shielburn Farmwind farm | wind farm | 6.9 | operationalupdated May 2013 | Dec 2009 | granted Oct 2012 | May 2013 |
| Boy's Hill Wind Clusterwind farm | wind farm | 6.9 | refusedupdated Feb 2014 | Jan 2013 | refused Oct 2013 | Feb 2014 |
| Hill of Fiddeswind farm | wind farm | 6.9 | operationalupdated May 2012 | Sep 2007 | granted Apr 2008 | May 2012 |
| Hill of Skilmafilly Cloffrickford (Denmore) Wind Farmwind farm | wind farm | 6.9 | operationalupdated May 2015 | Mar 2011 | granted Jan 2013 | May 2015 |
| Lodge Hillwind farm | wind farm | 6.9 | refusedupdated Jul 2014 | Jun 2012 | refused Jun 2014 | Jul 2014 |
| Brucklaywaird Wind Farmwind farm | wind farm | 6.9 | refusedupdated May 2015 | Feb 2014 | refused Apr 2015 | May 2015 |
| Deuchrieswind farm | wind farm | 6.9 | operationalupdated Oct 2018 | Nov 2012 | granted Apr 2014 | Oct 2018 |
Smaller schemes under 1 MW, mostly rooftop solar (40)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Donald Russell, Carnie Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Jan 2024 | Feb 2024 |
| Upper Dagie, Torphinswind turbine | wind turbine | 0.8 | approved, not builtupdated Oct 2024 | May 2024 | granted Oct 2024 | Oct 2024 |
| St Johns Wells, Fyviewind turbine | wind turbine | 0.8 | application submitted may be out of dateupdated Aug 2024 | Jul 2024 | — | Aug 2024 |
| Mcrae Seafoods, Watermill Roadsolar farm | solar farm | 0.8 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 |
| Edzell Airbase Wind Turbinewind turbine | wind turbine | 0.7 | application submitted may be out of dateupdated Apr 2023 | Mar 2023 | — | Apr 2023 |
| Upper Culphin, Cornhillwind turbine | wind turbine | 0.7 | application submitted | May 2026 | — | — |
| Upper Mains Farmwind turbine | wind turbine | 0.5 | application submitted may be out of dateupdated Nov 2023 | Nov 2023 | — | Nov 2023 |
| One Subsea, Badentoy Avenuerooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Jan 2023 | Nov 2022 | granted Dec 2022 | Jan 2023 |
| Ellismosssolar farm | solar farm | 0.4 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 |
| Badentoy Drive, Portlethenrooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Jan 2022 | Jan 2022 | granted Mar 2022 | Jan 2022 |
| Jacobshall, Gamriewind turbine | wind turbine | 0.3 | approved, not builtupdated Sep 2024 | Oct 2023 | granted Sep 2024 | Sep 2024 |
| Ferniebrae Barraswind turbine | wind turbine | 0.3 | approved, not builtupdated Feb 2026 | Dec 2024 | granted Dec 2025 | Feb 2026 |
| Lunar Freezing & Cold Storage, Sandhaven Roadrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Sep 2022 | Aug 2022 | granted Sep 2022 | Sep 2022 |
| Laeso Fish, Damhead Circlerooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 |
| Mcrae Seafoodssolar farm | solar farm | 0.3 | approved, not builtupdated Oct 2024 | Aug 2024 | granted Oct 2024 | Oct 2024 |
| Archer House, Main Road, Blackburnrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Jul 2022 | Jul 2022 | granted Aug 2022 | Jul 2022 |
| Logierieve Farm, Udnysolar farm | solar farm | 0.2 | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 |
| Little Elrick, Maudwind turbine | wind turbine | 0.2 | approved, not builtupdated May 2025 | Nov 2024 | granted Apr 2025 | May 2025 |
| Lan At Hilton, Park Farmwind turbine | wind turbine | 0.2 | application submittedupdated Dec 2025 | Dec 2025 | — | Dec 2025 |
| Wagglehill, Cuminestownwind turbine | wind turbine | 0.2 | refusedupdated Jul 2024 | Apr 2024 | refused Jun 2024 | Jul 2024 |
| HydroGlen Project - Glensaugh Farmsolar farm | solar farm | 0.2 | application submitted may be out of dateupdated Mar 2024 | Feb 2024 | — | Mar 2024 |
| Henderson Roadrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Feb 2022 | Jan 2022 | granted Mar 2022 | Feb 2022 |
| Blackiemuirsolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Nov 2022 | Sep 2022 | granted Nov 2022 | Nov 2022 |
| Forest Farm Dairy, Glasgoforestrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Dec 2022 | Nov 2022 | granted Dec 2022 | Dec 2022 |
| G & J Jack, Harbour Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | May 2023 | granted Aug 2023 | Sep 2023 |
| Oeg offshore, Tofthills Wayrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 |
| Hallmoss Workshop, Inverallochyrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2022 | Oct 2021 | granted Dec 2021 | Jan 2022 |
| Enterprise Driverooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated May 2022 | May 2022 | granted Jul 2022 | May 2022 |
| Castleton Farm Shopsolar farm | solar farm | 0.2 | application submitted | May 2026 | — | — |
| Mains Of Haulkertonrooftop solar | rooftop solar | 0.1 | approved, not built may be out of dateupdated May 2022 | May 2022 | granted Jun 2022 | May 2022 |
| Balmacassie Brae, Balmacassie Commercial Park Wind Power Towerwind farm | wind farm | 0.1 | application withdrawnupdated Jan 2026 | Aug 2024 | — | Jan 2026 |
| St Fergus Renewable Energy Parkbattery storage | battery storage | — | under constructionupdated Feb 2023 | Dec 2019 | granted Jul 2021 | Feb 2023 |
| Hillhead Of Gask, Longhaven -Battery Storagebattery storage | battery storage | — | under constructionupdated Feb 2026 | Jan 2022 | granted Apr 2022 | Feb 2026 |
| Kincraig Solar Farm and battery storage systembattery storage | battery storage | — | under constructionupdated Jun 2025 | Apr 2022 | granted Oct 2022 | Jun 2025 |
| Coast Viners Animal Nutrition, Drumlithie Solar Array & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Feb 2023 | Aug 2022 | granted Feb 2023 | Feb 2023 |
| Netherton, Fisherfordwind turbine | wind turbine | — | application submitted may be out of dateupdated Mar 2023 | Mar 2023 | — | Mar 2023 |
| HydroGlen Project - Glensaugh Farmbattery storage | battery storage | — | application submitted may be out of dateupdated Mar 2024 | Feb 2024 | — | Mar 2024 |
| Logierieve Farm, Udnywind farm | wind farm | — | application submittedupdated Nov 2024 | Oct 2024 | — | Nov 2024 |
| Middleton Of Rorasolar farm | solar farm | — | approved, not builtupdated Aug 2025 | Mar 2025 | granted Jul 2025 | Aug 2025 |
| Brigstanes Farm, Catterlinewind farm | wind farm | — | application submitted | May 2026 | — | — |
111 more projects not listed (furthest or smallest).
Postcode districts in Aberdeenshire
| District | Projects within 10 km | Pending | Approved | Operational |
|---|---|---|---|---|
| AB30 | 21 | 4 | 4 | 6 |
| AB31 | 4 | 3 | 0 | 0 |
| AB32 | 21 | 3 | 15 | 2 |
| AB33 | 7 | 0 | 2 | 1 |
| AB34 | 1 | 0 | 0 | 0 |
| AB35 | 1 | 0 | 0 | 1 |
| AB36 | 0 | 0 | 0 | 0 |
| AB39 | 15 | 2 | 6 | 3 |
| AB41 | 24 | 6 | 3 | 5 |
| AB42 | 25 | 3 | 13 | 5 |
| AB43 | 26 | 2 | 13 | 4 |
| AB44 | 16 | 1 | 2 | 9 |
| AB45 | 23 | 2 | 4 | 11 |
| AB51 | 16 | 4 | 7 | 3 |
| AB52 | 15 | 3 | 1 | 2 |
| AB53 | 16 | 2 | 1 | 6 |
| AB54 | 10 | 1 | 2 | 3 |
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Aberdeenshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.