Energy Projects Near You

Flushing, Longside (400 MW battery storage)

Flushing, Longside is a 400 MW battery storage project in Aberdeenshire, Scotland. Its status: consented by Scottish Ministers on 21 October 2026, not yet built (Scottish Government Energy Consents Unit). The Renewable Energy Planning Database (July 2026 extract) still records: application submitted on 4 July 2025, no decision recorded; the record was last updated on 13 October 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtstatus (Scottish Government Energy Consents Unit; status in REPD: application submitted)
13 October 2025record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
4 July 2025Application submitted
21 October 2026Consent granted (Scottish Ministers)

Status source: Scottish Government Energy Consents Unit. The Renewable Energy Planning Database (July 2026 extract) still shows this project as “application submitted”.

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status
approved, not built (Scottish Government Energy Consents Unit; REPD: application submitted)
Record last updated
13 October 2025
Operator or applicant
Harmony Energy Storage
Planning authority
Scottish Government (S36)
Planning application reference
ECU00006086
Address (REPD)
North of Longside Road, Flushing
Council area (by location)
Aberdeenshire
Name in REPD
Flushing, Longside - Battery Energy Storage System
REPD reference
18195

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Netherton, Langside Roadbattery storage400application submitted2.2
Greystone, Blackhillsbattery storage500application submitted5.7
Hill of Bracowind farm20application withdrawn6.0
Hillhead Of Gask, Longhavensolar farm14.2under construction6.5
St Fergus Moss Wind Farmwind farm6operational6.7
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm50approved, not built6.8
Salamander Offshore Wind Farm Battery Storage and Onshore Connectionbattery storage180approved, not built7.0
St Fergus Renewable Energy Parksolar farm5under construction7.4
South of Greenwellheadssolar farm5abandoned7.8

Status and events credited to a named source are from that source; other dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.5119, -1.9139).