Energy Projects Near You

Greystone, Blackhills (500 MW battery storage)

Greystone, Blackhills is a 500 MW battery storage project in Aberdeenshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 4 July 2025, no decision recorded; the record was last updated on 6 October 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWbattery storage
application submittedstatus in REPD
6 October 2025record last updated
Aberdeenshirecouncil area

Planning timeline

DateStage
4 July 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
500 MW
Status (REPD)
application submitted
Record last updated
6 October 2025
Operator or applicant
Peterhead Flexpower
Planning authority
Scottish Government (S36)
Planning application reference
ECU00006204
Address (REPD)
The W/O Greystone, Blackhills, Peterhead
Council area (by location)
Aberdeenshire
Name in REPD
Greystone, Blackhills - Battery Energy Storage System
REPD reference
19212

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hillhead Of Gask, Longhavensolar farm14.2under construction1.4
Netherton, Langside Roadbattery storage400application submitted3.7
Hill of Bracowind farm20application withdrawn5.6
Flushing, Longsidebattery storage400application submitted5.7
Salamander Offshore Wind Farm Battery Storage and Onshore Connectionbattery storage180approved, not built7.5
Fraserburgh Road - Kirkton Solar PV Farm & Energy Storage Facilitysolar farm50approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.4748, -1.8476).